CR-2026-002The Chamber’s New Headquarters Building
Add a third basement level to the conference and general-assembly hall
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 1.9MCurrent budgetSAR 57.1M
After the changeSAR 59M
+3.4%
Schedule
+60 d- Baseline finish2027-05-01
- New finish2027-06-30
Risk
+3Raises the chance of extension claims
Benefits
+9%420 more parking spaces for visitors and staff
+9% of expected benefits
Reason for change
An updated parking study expects a shortfall for visitors and staff once the conference & general-assembly hall opens and hosts the annual general assembly
Justification
Building it now costs about 60% less than a car-park building later, and eases congestion around HQ
PMO recommendation
Approve with conditionsThe PMO recommends approval with a fixed unit rate for the concrete works
Conditions
- Fix the unit rate for concrete works
Approval workflow
Submitted
Eng. Ahmed Y. Asiri
Done2026-03-02
PM review
Eng. Ahmed Y. Asiri
Done2026-03-03
Impact analysis
Karim Haddad
Done2026-03-07
Finance & procurement
Munirah A. Al-Khalidi
Done2026-03-08
Project owner’s acceptance
Eng. Bandar M. Al-Shammari
Done2026-03-08
Change committee recommendation
Dr. Mohammed I. Al-Subaie
Done2026-03-19
Executive Committee decision
Dr. Abdullah S. Al-Qahtani
Done2026-03-22
Baseline updated
Eng. Ahmed Y. Asiri
Done2026-03-26
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMajorAbove SAR 250K or 90 days
- A cost impact of SAR 1.9M is above SAR 250K — «major»: the Change Committee recommends and the Executive Committee decides.
- It has a financial link, so Finance & Procurement take part before the decision.
- It changes scope or deliverables, so the project owner must accept it.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saChairApprove
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@chamber.saYouApprove
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.saApprove
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saApprove
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.saApprove
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saApprove
- Approve6
- Approve with conditions0
- Reject0
- Abstain0
Decided by the committee on 22 March 2026The decision in the log · DEC-2026-009
Baseline
Baseline updated on 26 March 2026