Corrective plans for serious delay: actions, owners, dates, approval and follow-up, and the projects that need one.
this year, in your scope
followed weekly
or sent back
projects without a plan the rule asks for
past their dates
across the plans
When a corrective plan is required
An active project needs a corrective plan when its forecast finish is more than 40 days past the baseline, or its schedule performance index (SPI) falls below 0.85.
Slip past the baseline
> 40
Schedule performance index
< 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
The rule applies and no plan has been prepared yet.
Corrective plan requiredOff track
The Chamber’s New Headquarters Building74 days lateSPI 0.82Eng. Ahmed Y. Asiri
Corrective plan requiredOff track
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City95 days lateSPI 0.78Eng. Fahad T. Al-Sulami
Corrective plan requiredAt risk
Smart Access, Visitor & Event Management at HQ & the Branches45 days lateSPI 0.88Eng. Waleed O. Al-Juhani
Corrective plan requiredAt risk
Correspondence & Document Management System46 days lateSPI 0.95Dana S. Al-Saleh
The plan, its status, what triggered it, its actions, the days won back and its approval.
Display options
| Owner | Next step | ||||||
|---|---|---|---|---|---|---|---|
CP-2026-01 · Version 2 My Business Portal 2.0 — the Unified Member Journey | Awaiting approval | 48 days lateSPI 0.85 | 1 of 6 doneOverdue: 1 | 6 of 21 | 2027-05-12 | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | Programme manager · Eng. Reem K. Al-Dosari |
CP-2026-02 · Version 1 Converting the Current Headquarters into a Member Services Centre & Committee Rooms | Approved — under way | 104 days lateSPI 0.76 | 1 of 5 doneOverdue: 1 | 0 of 45 | 2027-02-03 | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | — |
CP-2026-03 · Version 1 Training & Employment Centre Complex | Awaiting approval | 131 days lateSPI 0.72 | 0 of 4 doneOverdue: 1 | 0 of 60 | 2027-06-01 | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Project Management Office · Dr. Noura M. Al-Otaibi |
CP-2026-04 · Version 1 The Chamber’s Investment Building — Business Tower on King Fahd Road | Approved — under way | 55 days lateSPI 0.83 | 1 of 5 done | 0 of 33 | 2027-08-03 | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | — |
CP-2026-05 · Version 1 Chamber ERP on Dynamics 365 | Sent back | 52 days lateSPI 0.83 | 1 of 4 done | 10 of 32 | 2027-02-27 | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Project Approval Committee · Dr. Noura M. Al-Otaibi |