Portfolios

The six portfolios with their financial and schedule performance and health.

2027 portfolio plan
Portfolio budget
SAR 272.6M

6 portfolios · FY 2026

Spent to date
SAR 120.7M

⁦44%⁩ of budget

Forecast cost
SAR 283.8M+4.1%

Estimate at completion

Expected portfolio value
SAR 422.3M

Benefits over the projects’ life

Average health score
59

Budget-weighted

Investment across portfolios

Each portfolio’s share of the approved budget, with its estimate at completion above it.

⁦50%⁩New Headquarters & Investment Assets Portfolio · SAR 136.5M · ⁦50.1%⁩⁦25%⁩Branches, Service & Training Centres Portfolio · SAR 67M · ⁦24.6%⁩⁦12%⁩Building Rehabilitation & Sustainability Portfolio · SAR 33.6M · ⁦12.3%⁩⁦7%⁩Technology & Enterprise Systems Portfolio · SAR 18.3M · ⁦6.7%⁩Member Services & Business Voice Portfolio · SAR 15.2M · ⁦5.6%⁩Institutional Excellence & Capability Portfolio · SAR 2M · ⁦0.7%⁩
  • New Headquarters & Investment Assets Portfolio136.5M⁦+1.5%⁩EAC SAR 138.5M
  • Branches, Service & Training Centres Portfolio67M⁦+9.9%⁩EAC SAR 73.7M
  • Building Rehabilitation & Sustainability Portfolio33.6M⁦+8.0%⁩EAC SAR 36.3M
  • Technology & Enterprise Systems Portfolio18.3M⁦+3.0%⁩EAC SAR 18.8M
  • Member Services & Business Voice Portfolio15.2M⁦−2.0%⁩EAC SAR 14.9M
  • Institutional Excellence & Capability Portfolio2M⁦−23.8%⁩EAC SAR 1.5M

Portfolios

Each portfolio with its manager, owner, budget, financial and schedule performance and expected value.

52
PF-CAP·4 projects·2 programmes

Branches, Service & Training Centres Portfolio

The Training & Employment Centre complex, the Second Industrial City branch, the new Premium Members Centre and the Wadi Al-Dawasir branch.

Add to comparisonQuick look

Approved budget

67M

EAC

73.7M⁦+9.9%⁩

Expected value

95MRealised ⁦1%⁩

Schedule performance · Financial performance

SPI0.79Schedule performance index · 0.79CPI0.88Cost performance index · 0.88
32.9M/ 67M6.7Mprojected overrun(⁦9.9%⁩)
Off track
ManagerEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipManagerP-014ab.alharbi@chamber.saOwnerEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentOwnerP-049s.alfraih@chamber.sa
58
PF-INF·8 projects·2 programmes

New Headquarters & Investment Assets Portfolio

The new headquarters, the investment tower, the conference and exhibition hall and the entrepreneurship centre, with smart access, the network, the studio and the unified contact centre.

Add to comparisonQuick look

Approved budget

136.5M

EAC

138.5M⁦+1.5%⁩

Expected value

210MRealised ⁦3%⁩

Schedule performance · Financial performance

SPI0.87Schedule performance index · 0.87CPI0.95Cost performance index · 0.95
46.1M/ 136.5M2Mprojected overrun(⁦1.5%⁩)
Off track
ManagerEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesManagerP-013b.alshammari@chamber.saOwnerSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesOwnerP-012s.alqarni@chamber.sa
61
PF-SUS·5 projects·1 programme

Building Rehabilitation & Sustainability Portfolio

Turning the current headquarters into a service centre with committee rooms, rehabilitating the Shaqra and Business Centre branches, solar power and energy efficiency.

Add to comparisonQuick look

Approved budget

33.6M

EAC

36.3M⁦+8.0%⁩

Expected value

55MRealised ⁦10%⁩

Schedule performance · Financial performance

SPI0.83Schedule performance index · 0.83CPI0.90Cost performance index · 0.90
23.5M/ 33.6M2.7Mprojected overrun(⁦8.0%⁩)
Off track
ManagerEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityManagerP-028m.alotaibi@chamber.saOwnerSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesOwnerP-012s.alqarni@chamber.sa
71
PF-TECH·7 projects·2 programmes

Technology & Enterprise Systems Portfolio

Technology infrastructure, cloud, cybersecurity and disaster recovery, the Dynamics 365 systems for resources and members, documents and self-service.

Add to comparisonQuick look

Approved budget

18.3M

EAC

18.8M⁦+3.0%⁩

Expected value

26MRealised ⁦17%⁩

Schedule performance · Financial performance

SPI0.91Schedule performance index · 0.91CPI0.94Cost performance index · 0.94
12.3M/ 18.3M549Kprojected overrun(⁦3.0%⁩)
At risk
ManagerEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyManagerP-017n.albuqami@chamber.saOwnerEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITOwnerP-011m.alrasheed@chamber.sa
74
PF-DT·7 projects·2 programmes

Member Services & Business Voice Portfolio

The My Business portal and app, certificate-of-origin automation and the dispute-settlement platform, the business observatory, the committee recommendations tracker and the Riyadh Economic Forum.

Add to comparisonQuick look

Approved budget

15.2M

EAC

14.9M⁦−2.0%⁩

Expected value

32MRealised ⁦14%⁩

Schedule performance · Financial performance

SPI0.92Schedule performance index · 0.92CPI0.98Cost performance index · 0.98
4.9M/ 15.2M302Kprojected saving(⁦2.0%⁩)
At risk
ManagerFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceManagerP-003f.alshehri@chamber.saOwnerEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITOwnerP-011m.alrasheed@chamber.sa
84
PF-INS·5 projects·1 programme

Institutional Excellence & Capability Portfolio

The strategy’s operational plans, performance measurement and risk management, the entrepreneurship fast track and the e-learning platform.

Add to comparisonQuick look

Approved budget

2M

EAC

1.5M⁦−23.8%⁩

Expected value

4.3MRealised ⁦40%⁩

Schedule performance · Financial performance

SPI0.98Schedule performance index · 0.98CPI1.00Cost performance index · 1.00
878K/ 2M475Kprojected saving(⁦23.8%⁩)
On track
ManagerDr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Project Management OfficeManagerP-002n.alotaibi@chamber.saOwnerSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesOwnerP-012s.alqarni@chamber.sa

Portfolio map

Risk across, strategic value up, bubble size by budget.

Portfolio map
  • Member Services & Business Voice Portfolio
  • Branches, Service & Training Centres Portfolio
  • Technology & Enterprise Systems Portfolio
  • Building Rehabilitation & Sustainability Portfolio
  • New Headquarters & Investment Assets Portfolio
  • Institutional Excellence & Capability Portfolio
Approved budget · SAR 136.5M
Portfolio map
CategoryRisk scoreStrategic valueApproved budgetChart legend
New Headquarters & Investment Assets Portfolio71.088.0SAR 136.5MNew Headquarters & Investment Assets Portfolio
Branches, Service & Training Centres Portfolio80.075.0SAR 67MBranches, Service & Training Centres Portfolio
Building Rehabilitation & Sustainability Portfolio70.080.0SAR 33.6MBuilding Rehabilitation & Sustainability Portfolio
Technology & Enterprise Systems Portfolio56.074.0SAR 18.3MTechnology & Enterprise Systems Portfolio
Member Services & Business Voice Portfolio40.077.0SAR 15.2MMember Services & Business Voice Portfolio
Institutional Excellence & Capability Portfolio20.064.0SAR 2MInstitutional Excellence & Capability Portfolio

Schedule and cost indices

Budget-weighted; below 0.90 is off track.

Schedule performance indexCost performance index
Member Services & Business Voice Portfolio
SPI 0.92CPI 0.98
Branches, Service & Training Centres Portfolio
SPI 0.79CPI 0.88
Technology & Enterprise Systems Portfolio
SPI 0.91CPI 0.94
Building Rehabilitation & Sustainability Portfolio
SPI 0.83CPI 0.90
New Headquarters & Investment Assets Portfolio
SPI 0.87CPI 0.95
Institutional Excellence & Capability Portfolio
SPI 0.98CPI 1.00
0.700.800.901.001.10