Portfolio · PF-SUS

Building Rehabilitation & Sustainability Portfolio

Off track

Turning the current headquarters into a service centre with committee rooms, rehabilitating the Shaqra and Business Centre branches, solar power and energy efficiency.

What-if scenarios
Approved budget
SAR 33.6M

incl. SAR 1.1M unallocated reserve

Actual spend
SAR 23.5M

⁦70%⁩ of budget

EAC
SAR 36.3M+8.0%

Estimate at completion

Expected value
SAR 55M

⁦10%⁩ realised

Health score
61−5

was ⁦66⁩ in May

Manager

Eng. Mishari K. Al-Otaibi

Director, Sustainability & Social Responsibility

Owner

Sarah A. Al-Qarni

Assistant Secretary-General, Support Services

Programmes5 projects

Building Rehabilitation & Efficiency Programme⁦55%⁩
On track 3Critical 1On hold 1

AI insight

Every active project in the portfolio is on track

No project is off track or critical; the weakest health dimension is “Risk” at ⁦40⁩.

Confidence⁦78%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
Converting the Current Headquarters into a Member Services Centre & Committee Rooms83.0⁦24.4%⁩⁦68%⁩⁦16.6%⁩
Solar Power for the Chamber’s Buildings & Branches71.0⁦20.9%⁩⁦58%⁩⁦12.1%⁩
Business Centre (Exit 6) Branch Rehabilitation65.0⁦19.1%⁩⁦97%⁩⁦18.5%⁩
Shaqra Branch Rehabilitation62.0⁦18.2%⁩⁦36%⁩⁦6.6%⁩
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)Suspended — progress frozen59.0⁦17.4%⁩⁦6%⁩⁦1.0%⁩
Portfolio progress⁦54.9%⁩

How it is computed

⁦54.9%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦0⁩
  • · For comparison: weighting by budget alone gives ⁦64.4%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

61At risk
DimensionScoreWeightPoints
Schedule52⁦20%⁩10.4
Cost64⁦20%⁩12.8
Risk40⁦15%⁩6.0
Scope72⁦10%⁩7.2
Quality74⁦10%⁩7.4
Resources60⁦10%⁩6.0
Stakeholders76⁦5%⁩3.8
Benefits74⁦10%⁩7.4
Total61

Health-score trend

May – October 2026

6661

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • Critical
  • On hold
Approved budget · SAR 20.6M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Converting the Current Headquarters into a Member Services Centre & Committee RoomsPRJ-2026-004·Priority score 87Critical
  2. 2Solar Power for the Chamber’s Buildings & BranchesPRJ-2026-010·Priority score 83On track
  3. 3Shaqra Branch RehabilitationPRJ-2026-025·Priority score 70On track
  4. 4Business Centre (Exit 6) Branch RehabilitationPRJ-2026-036·Priority score 69On track
  5. 5Energy Retrofit of the Chamber’s Existing Buildings (ESCO)PRJ-2026-026·Priority score 58On hold

Portfolio priorities 2026–2027

  • Rescue the conversion of the current headquarters into a member services centreCritical — an executive-committee task force is in place.
  • Lift rehabilitated existing chamber buildings and branches to 55%43% today — behind the path to the 2027 target.
  • Secure funding for the ESCO energy retrofitOn hold since the executive committee’s 6 October decision.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 33.6MSAR 33.6M
Unallocated reserve−SAR 1.1MSAR 32.5M
Building Rehabilitation & Efficiency Programme+SAR 3.8MSAR 36.3M
Estimate at completionSAR 36.3MSAR 36.3M

Budget use

23.5M/ 33.6M2.7Mprojected overrun(⁦8.0%⁩)
Actual spend
23.5M
Committed
29.8M
Approved budget
33.6M
Estimate at completion
36.3M

Expected-value mix

Expected-value mix

SAR 55M

Expected value

  • Sustainability (ESG)SAR 24.2M⁦44%⁩
  • Cost savingSAR 20.9M⁦38%⁩
  • Beneficiary satisfactionSAR 9.9M⁦18%⁩
Expected-value mix
CategoryValueShare
Sustainability (ESG)SAR 24.2M⁦44%⁩
Cost savingSAR 20.9M⁦38%⁩
Beneficiary satisfactionSAR 9.9M⁦18%⁩
TotalSAR 55M⁦100%⁩

SAR 5.2M

Expected value SAR 55M

⁦73%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦5⁩ results
Export CSV
Converting the Current Headquarters into a Member Services Centre & Committee RoomsPRJ-2026-004PG-094ExecutionCritical⁦68%⁩⁦24.4%⁩P1P1 · Top priority — score ⁦87⁩ of 10020.6M24.5M⁦+19.0%⁩0.74Schedule performance index · 0.740.84Cost performance index · 0.84Risk score · Weak
Solar Power for the Chamber’s Buildings & BranchesPRJ-2026-010PG-094ExecutionOn track⁦58%⁩⁦20.9%⁩P1P1 · Top priority — score ⁦83⁩ of 1004.8M4.8M⁦−1.0%⁩1.02Schedule performance index · 1.021.01Cost performance index · 1.01Risk score · Good
Business Centre (Exit 6) Branch RehabilitationPRJ-2026-036PG-095ClosureOn track⁦97%⁩⁦19.1%⁩P2P2 · High priority — score ⁦69⁩ of 1003.4M3.3M⁦−1.0%⁩0.98Schedule performance index · 0.981.01Cost performance index · 1.01Risk score · Excellent
Shaqra Branch RehabilitationPRJ-2026-025PG-094ExecutionOn track⁦36%⁩⁦18.2%⁩P2P2 · High priority — score ⁦70⁩ of 1002.1M2.1M⁦−2.0%⁩1.03Schedule performance index · 1.031.02Cost performance index · 1.02Risk score · Good
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)PRJ-2026-026PG-093PlanningOn hold⁦8%⁩⁦17.4%⁩P3P3 · Medium priority — score ⁦58⁩ of 1001.7M1.7M⁦0.0%⁩0.89Schedule performance index · 0.891.00Cost performance index · 1.00Risk score · Weak
Total · 532.5M36.3M
⁦1⁩–⁦5⁩ of ⁦5⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Latest on this portfolio

6 October 2026

  1. Rejection: Executive Committee Hold DEC-2026-035ESCO energy retrofit put on hold pending funding

    2026-10-06 10:00

30 September 2026

  1. Gate decision: Project Approval Committee Go DEC-2026-034Mid-delivery review passed for the chamber’s solar project

    2026-09-30 10:00

22 September 2026