Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦95%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.74⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦68% done against 92% planned⁩.

⁦SPI 0⁩.⁦74⁩, ⁦CPI 0⁩.⁦84⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.2A better member experience and service quality

Main initiative

SI-1.2.1Existing buildings & committee rooms

Contribution to the initiative⁦86%⁩

The project’s share of the initiative’s project budget (2 projects)

Annual work-plan line
WP-2024-004
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦68%⁩

Awaiting acceptance ⁦9%⁩

Not handed in ⁦23%⁩

8 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Supply⁦11%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Installation⁦9%⁩

Corrective planCP-2026-02

Approved — under wayOverdue: ⁦1⁩

The main contractor’s cash-flow distress and unpaid subcontractors, the underground tanks failing the tightness test, and committee-room wing changes never shown to Civil Defence

Actions

⁦1⁩ of ⁦5⁩ done

Next: Appoint an independent financial adviser to audit contractor liquidity · Khalid N. Al-Mutairi · 2026-10-20

Days won back

⁦0⁩ of ⁦45⁩

With the plan: 2027-02-03

Open the plan

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦98%⁩ of budget

16.7M/ 20.6M3.9Mprojected overrun(⁦19.0%⁩)
Actual spend
16.7M
Committed
20.2M
Approved budget
20.6M
Estimate at completion
24.5M

Next milestones

  • Closure⁦2027-02-03⁩was ⁦2026-09-30⁩Late

Waiting on someone

⁦1⁩ approval and ⁦3⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦3⁩ open

  • Appoint an independent financial adviser to audit contractor liquidityKhalid N. Al-Mutairi8 days overdue2026-10-209 Jumada I 1448 AHCritical
  • Pay subcontractors directly from the next certificateMunirah A. Al-KhalidiIn 8 days2026-11-0525 Jumada I 1448 AHCritical
  • Re-run the water-tightness test on the underground tanksEng. Waleed O. Al-JuhaniIn 5 days2026-11-0222 Jumada I 1448 AHHigh

Risks & impediments

3 open risks, exposure SAR 2.7M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩1Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩RSK-0021Main contractor cash-flow distress and unpaid subcontractors
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩1Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0023Central HVAC failures during commissioning1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0022Fire-fighting and evacuation systems failing Civil Defence requirements
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High1
  • Medium1
  • Low0

Deliverables

⁦8⁩ of ⁦12⁩ approved

  • Project plan & baseline004-D1 · V1 · CRT-004-01⁦3%⁩Eng. Waleed O. Al-Juhani⁦2024-05-19⁩2024-05-1911 Dhuʻl-Qiʻdah 1445 AHApproved
  • Monitoring & reporting004-D2 · V1 · CRT-004-02⁦3%⁩Eng. Bandar M. Al-Shammari⁦2024-08-05⁩2024-08-051 Safar 1446 AHApproved
  • Detailed design004-D3 · V1 · CRT-004-03⁦6%⁩Eng. Bandar M. Al-Shammari⁦2024-10-23⁩2024-10-2320 Rabiʻ II 1446 AHApproved
  • Permits & approvals004-D4 · V1 · CRT-004-04⁦6%⁩Sarah A. Al-Qarni⁦2025-01-09⁩2025-01-099 Rajab 1446 AHApproved
  • Site works & excavation004-D5 · V1 · CRT-004-05⁦13%⁩Sarah A. Al-Qarni⁦2025-03-29⁩2025-03-2929 Ramadan 1446 AHApproved
  • Structure004-D6 · V1 · CRT-004-06⁦13%⁩Eng. Waleed O. Al-Juhani⁦2025-06-16⁩2025-06-1620 Dhuʻl-Hijjah 1446 AHApproved
  • Finishes004-D7 · V1 · CRT-004-07⁦13%⁩Eng. Bandar M. Al-Shammari⁦2025-09-02⁩2025-09-0210 Rabiʻ I 1447 AHApproved
  • Supply004-D8 · V1 · CRT-004-08⁦11%⁩Eng. Waleed O. Al-Juhani⁦2025-11-20⁩2025-11-2029 Jumada I 1447 AHApproved
  • Installation004-D9 · V1⁦9%⁩Eng. Bandar M. Al-Shammari264 days overdue2026-02-0618 Shaʻban 1447 AHSubmitted
  • Testing & commissioning004-D10 · V0⁦9%⁩Sarah A. Al-Qarni185 days overdue2026-04-269 Dhuʻl-Qiʻdah 1447 AHDraft
  • Provisional acceptance004-D11 · V0⁦7%⁩Eng. Bandar M. Al-Shammari107 days overdue2026-07-1328 Muharram 1448 AHDraft
  • Final acceptance004-D12 · V0⁦7%⁩Sarah A. Al-Qarni28 days overdue2026-09-3019 Rabiʻ II 1448 AHDraft

Team, contracts & documents

Team

4 members

Eng. Waleed O. Al-Juhani · Director, Facilities Operations & MaintenanceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreHaifa S. Al-Ruwaili · Senior Financial Analyst
  • Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceProject managerP-021w.aljuhani@chamber.sa⁦70%⁩
  • Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreBeneficiary lead — committee and training roomsP-010t.alanazi@chamber.sa⁦20%⁩
  • Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystFinancial analystP-037h.alruwaili@chamber.sa⁦15%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close