Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Remove from watchlistRebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
SAR +3.9M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth