PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

APPROVEDV2Approved ⁦2024-01-12⁩

1Project identity

Required at this stage
Project name
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Project code
PRJ-2026-004
Project sponsor
Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa
Project manager
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa
Portfolio & programme
Building Rehabilitation & Sustainability PortfolioBuilding Rehabilitation & Efficiency Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

⁦Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings⁩, and a modern members’ service hall.

3Objectives

Required at this stage
  1. 1A better member experience and service quality
  2. 2Active sectoral committees and business challenges resolved

4Scope

Required at this stage

In scope

  • ⁦Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings⁩, and a modern members’ service hall.
  • Saudi Building Code compliance
  • An approved plan to keep member services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep member services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-02-23⁩
2Main deliverable — stage 1⁦2025-06-02⁩
3Main deliverable — final stage⁦2026-05-14⁩
4Final report⁦2026-09-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-01-12⁩
  2. Contract signed⁦2024-06-20⁩
  3. 50% of works complete⁦2025-06-02⁩
  4. Provisional acceptance⁦2026-07-13⁩
  5. Closure⁦2026-09-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩14.8M
  • Supervision & consulting⁦14.0%⁩2.9M
  • Internal team⁦9.0%⁩1.9M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩1M
The owning sector’s approved budgetTotal20.6M

9Timeline

Required at this stage
Start
2024-01-142 Rajab 1445 AH
Baseline finish
2026-09-3019 Rabiʻ II 1448 AH
Duration
⁦33⁩ months

10Key risks

Required at this stage
  • HighMain contractor cash-flow distress and unpaid subcontractors
  • HighFire-fighting and evacuation systems failing Civil Defence requirements
  • MediumCentral HVAC failures during commissioning

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the chamber
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close