A late current-HQ rehab holds up the specification and pushes Shaqra into summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
Programme · PG-09 · Building Rehabilitation & Sustainability Portfolio
Rehabilitating the current headquarters and the Shaqra and Business Centre branches, solar power and energy efficiency.
incl. SAR 750K programme reserve
71% of budget
Estimate at completion
Planned 61%
Cost performance index 0.90
Manager
Eng. Mishari K. Al-Otaibi
Director, Sustainability & Social Responsibility
Sponsor
Sarah A. Al-Qarni
Assistant Secretary-General, Support Services
Projects
5 projects
2024-01-14 — 2027-10-31
On track 3Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
Bring 55% of existing chamber buildings and branches up to civil-defence and energy-efficiency standards
15% of chamber building energy from renewables
Cut chamber building emissions 12% from baseline
From baseline to target
Existing buildings and branches rehabilitated
by 2027Renewable energy share
by 2026Energy-bill savings
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Shaqra rehab applies the standard rehabilitation specification approved at the current HQ
Lessons from the Exit 6 fire and alarm works are applied in Shaqra
The retrofit builds on the solar metering in the chamber’s buildings
Risks that hit more than one project, managed at programme level.
A late current-HQ rehab holds up the specification and pushes Shaqra into summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
5 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 1 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 1 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Members within 30 minutes of a branch or service point
76.4%
+1
Target 78.0%98%
Member satisfaction with service at headquarters and the branches
71%
+1
Target 72%99%
Savings from spend rationalisation
3.1SAR M
0
Target 4.372%
Committee and training halls fitted out this year (cumulative)
48halls
+4
Target 6080%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
ESCO energy retrofit put on hold pending funding
Executive Committee · 2026-10-06 · DEC-2026-035
Mid-delivery review passed for the chamber’s solar project
Project Approval Committee · 2026-09-30 · DEC-2026-034
Task force formed for the distressed contractor on the current-HQ rehabilitation
Executive Committee · 2026-09-22 · DEC-2026-032
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Converting the Current Headquarters into a Member Services Centre & Committee RoomsPRJ-2026-004 | Eng. Waleed O. Al-Juhani | 4Execution | Critical | 68% | 20.6M | 24.5M+19.0% | 0.74Schedule performance index · 0.74 | 0.84Cost performance index · 0.84 |
| Solar Power for the Chamber’s Buildings & BranchesPRJ-2026-010 | Eng. Mishari K. Al-Otaibi | 4Execution | On track | 58% | 4.8M | 4.8M−1.0% | 1.02Schedule performance index · 1.02 | 1.01Cost performance index · 1.01 |
| Shaqra Branch RehabilitationPRJ-2026-025 | Eng. Mishari K. Al-Otaibi | 4Execution | On track | 36% | 2.1M | 2.1M−2.0% | 1.03Schedule performance index · 1.03 | 1.02Cost performance index · 1.02 |
| Energy Retrofit of the Chamber’s Existing Buildings (ESCO)PRJ-2026-026 | Eng. Mishari K. Al-Otaibi | 3Planning | On hold | 8% | 1.7M | 1.7M0.0% | 0.89Schedule performance index · 0.89 | 1.00Cost performance index · 1.00 |
| Business Centre (Exit 6) Branch RehabilitationPRJ-2026-036 | Eng. Waleed O. Al-Juhani | 5Closure | On track | 97% | 3.4M | 3.3M−1.0% | 0.98Schedule performance index · 0.98 | 1.01Cost performance index · 1.01 |
| Total · 5 | 32.5M | 36.3M |
SAR 32.5M
Budget
| Category | Value | Share |
|---|---|---|
| Converting the Current Headquarters into a Member Services Centre & Committee Rooms | SAR 20.6M | 63% |
| Solar Power for the Chamber’s Buildings & Branches | SAR 4.8M | 15% |
| Shaqra Branch Rehabilitation | SAR 2.1M | 6% |
| Energy Retrofit of the Chamber’s Existing Buildings (ESCO) | SAR 1.7M | 5% |
| Business Centre (Exit 6) Branch Rehabilitation | SAR 3.4M | 10% |
| Total | SAR 32.5M | 100% |