Programme · PG-09 · Building Rehabilitation & Sustainability Portfolio

Building Rehabilitation & Efficiency Programme

Off track

Rehabilitating the current headquarters and the Shaqra and Business Centre branches, solar power and energy efficiency.

Approved budget
SAR 33.3M

incl. SAR 750K programme reserve

Actual spend
SAR 23.5M

⁦71%⁩ of budget

EAC
SAR 36.3M+11.7%

Estimate at completion

Progress
⁦55%⁩

Planned ⁦61%⁩

Schedule performance index
0.83

Cost performance index 0.90

Manager

Eng. Mishari K. Al-Otaibi

Director, Sustainability & Social Responsibility

Sponsor

Sarah A. Al-Qarni

Assistant Secretary-General, Support Services

Projects

5 projects

2024-01-14 — 2027-10-31

On track 3Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Bring 55% of existing chamber buildings and branches up to civil-defence and energy-efficiency standards

  2. 2

    15% of chamber building energy from renewables

  3. 3

    Cut chamber building emissions 12% from baseline

Programme benefits

From baseline to target

  • Existing buildings and branches rehabilitated

    by ⁦2027⁩
    Baseline 38Current 43 %Target 55
  • Renewable energy share

    by ⁦2026⁩
    Baseline 4Current 14.1 %Target 15
  • Energy-bill savings

    by ⁦2027⁩
    Baseline 0Current 480 SAR KTarget 1,100

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2024202520262027
2027-02-03
2026-11-12
2027-04-22
2027-09-30
2027-10-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The Shaqra rehab applies the standard rehabilitation specification approved at the current HQ

  • Lessons from the Exit 6 fire and alarm works are applied in Shaqra

  • The retrofit builds on the solar metering in the chamber’s buildings

Shared risks

Risks that hit more than one project, managed at programme level.

16

A late current-HQ rehab holds up the specification and pushes Shaqra into summer 2027

PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi

Affects

Open risks in the programme’s projects

5 risks

Open risks in the programme’s projects
  • Critical1
  • High2
  • Medium1
  • Low1
  • Risks 5
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical1 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low1 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Sarah A. Al-QarniManage closelyEng. Mishari K. Al-OtaibiManage closelyEng. Waleed O. Al-JuhaniManage closelyEng. Bandar M. Al-ShammariManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & IT
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & ITSarah A. Al-Qarni · Assistant Secretary-General, Support Services
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-10-28

Programme projects

The programme’s performance is computed from these projects.

⁦5⁩ results
Export CSV
Manager
Converting the Current Headquarters into a Member Services Centre & Committee RoomsPRJ-2026-004Eng. Waleed O. Al-Juhani4ExecutionCritical⁦68%⁩20.6M24.5M⁦+19.0%⁩0.74Schedule performance index · 0.740.84Cost performance index · 0.84
Solar Power for the Chamber’s Buildings & BranchesPRJ-2026-010Eng. Mishari K. Al-Otaibi4ExecutionOn track⁦58%⁩4.8M4.8M⁦−1.0%⁩1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Shaqra Branch RehabilitationPRJ-2026-025Eng. Mishari K. Al-Otaibi4ExecutionOn track⁦36%⁩2.1M2.1M⁦−2.0%⁩1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)PRJ-2026-026Eng. Mishari K. Al-Otaibi3PlanningOn hold⁦8%⁩1.7M1.7M⁦0.0%⁩0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Business Centre (Exit 6) Branch RehabilitationPRJ-2026-036Eng. Waleed O. Al-Juhani5ClosureOn track⁦97%⁩3.4M3.3M⁦−1.0%⁩0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Total · 532.5M36.3M
⁦1⁩–⁦5⁩ of ⁦5⁩

Budget shares

Budget shares

SAR 32.5M

Budget

  • Converting the Current Headquarters into a Member Services Centre & Committee RoomsSAR 20.6M⁦63%⁩
  • Solar Power for the Chamber’s Buildings & BranchesSAR 4.8M⁦15%⁩
  • Shaqra Branch RehabilitationSAR 2.1M⁦6%⁩
  • Energy Retrofit of the Chamber’s Existing Buildings (ESCO)SAR 1.7M⁦5%⁩
  • Business Centre (Exit 6) Branch RehabilitationSAR 3.4M⁦10%⁩
Budget shares
CategoryValueShare
Converting the Current Headquarters into a Member Services Centre & Committee RoomsSAR 20.6M⁦63%⁩
Solar Power for the Chamber’s Buildings & BranchesSAR 4.8M⁦15%⁩
Shaqra Branch RehabilitationSAR 2.1M⁦6%⁩
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)SAR 1.7M⁦5%⁩
Business Centre (Exit 6) Branch RehabilitationSAR 3.4M⁦10%⁩
TotalSAR 32.5M⁦100%⁩