Procurement
The procurement plan: packages, methods, evaluation and award.
Working on:Riyadh Chamber of Commerce & Industry
- Packages in the plan
- 18
- Estimated value
- SAR 39.3M
- In the market now
- 8
- Awaiting award
- 3
- Award savings
- SAR 30K
FY2026: 14 · FY2027: 4
FY2027 plan: SAR 7.3M
SAR 26.5M
With the procurement committee
7.1% below estimate
Ready-made views
Procurement timeline
Bars: planned spans of each step; diamonds: actual dates; gold line: today
Package
2025 Oct 2026Jan Apr Jul Oct 2027Jan Apr Jul
Prepare booklet Issue Bids close Evaluate Award Actual date Today
Dynamics 365 supplier-portal integration
The data is ready to exchange with the Dynamics 365 procurement module and supplier portal; automatic sync starts once the connector is switched on.
Integration-ready for the Dynamics 365 supplier portal
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
- Tender, bid and award fields mapped to the Dynamics 365 procurement data model
- A supplier-portal reference kept for every published package
- Awards linked to contracts and certificates in Munjaz
- Awaiting the connector permissions from Enterprise Systems
- Awaiting the integration interfaces for automatic sync
References ready to sync
Packages with a supplier-portal reference: 10
- Chamber conference & exhibition hall phase 1 — main works260614031187Awaiting link
- Chamber conference & exhibition hall — supervision260705031244Awaiting link
- Paper membership-file archive — scanning and automated indexing for Member 360261004031302Awaiting link
- Identity & access management licences260914031355Awaiting link
- Operational plans & scorecards for the chamber’s 2025–2030 strategy — advisory260224030418Awaiting link
- Entrepreneurship Fast Track platform & readiness assessment251006029877Awaiting link
- Training-track provider for the training centre’s e-learning platform261012031366Awaiting link