Original
Original baseline
- Finish
- 2026-09-30
- Budget
- SAR 19.5M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-01-14 · by Sarah A. Al-Qarni
Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
SAR +3.9M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-01-14 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Waleed O. Al-Juhani
What changed from version A to version B
Finish
2026-09-302027-03-08
+159 days
Budget
SAR 19.5MSAR 20.6M
+1.07 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference