Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−19

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦8% done against 9% planned⁩.

⁦SPI 0⁩.⁦89⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Improving the OrganisationSO-4.1Financial sustainability

Main initiative

SI-4.1.3Clean energy & efficient buildings

Contribution to the initiative⁦26%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2026-026
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦8%⁩

Awaiting acceptance ⁦6%⁩

Not handed in ⁦86%⁩

2 deliverables accepted

  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Detailed design⁦6%⁩

Progress & earned value

⁦2⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦9%⁩ of budget

132K/ 1.7M
Actual spend
132K
Committed
155K
Approved budget
1.7M
Estimate at completion
1.7M

Next milestones

  • 50% of works complete⁦2026-12-22⁩was ⁦2026-10-21⁩Late
  • Provisional acceptance⁦2027-08-20⁩was ⁦2027-05-20⁩Late
  • Closure⁦2027-10-31⁩was ⁦2027-06-30⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • ⁦Request ESCO funding in the 2027 budget⁩Haifa S. Al-RuwailiIn 18 days2026-11-155 Jumada II 1448 AHMedium

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 240K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0043Funding left out of the 2027 budget, keeping the tender suspendedProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium0
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦2⁩ of ⁦12⁩ approved

  • Project plan & baseline026-D1 · V1 · CRT-026-01⁦4%⁩Eng. Mishari K. Al-Otaibi⁦2026-04-07⁩2026-04-0719 Shawwal 1447 AHApproved
  • Monitoring & reporting026-D2 · V1 · CRT-026-02⁦4%⁩Eng. Bandar M. Al-Shammari⁦2026-05-18⁩2026-05-181 Dhuʻl-Hijjah 1447 AHApproved
  • Detailed design026-D3 · V1⁦6%⁩Eng. Bandar M. Al-Shammari122 days overdue2026-06-2813 Muharram 1448 AHSubmitted
  • Permits & approvals026-D4 · V0⁦6%⁩Sarah A. Al-Qarni81 days overdue2026-08-0825 Safar 1448 AHDraft
  • Site works & excavation026-D5 · V0⁦12%⁩Sarah A. Al-Qarni41 days overdue2026-09-176 Rabiʻ II 1448 AHDraft
  • Structure026-D6 · V0⁦12%⁩Eng. Mishari K. Al-OtaibiDue today2026-10-2817 Jumada I 1448 AHDraft
  • Finishes026-D7 · V0⁦12%⁩Eng. Bandar M. Al-ShammariIn 41 days2026-12-0828 Jumada II 1448 AHDraft
  • Supply026-D8 · V0⁦10%⁩Eng. Mishari K. Al-OtaibiIn 82 days2027-01-1810 Shaʻban 1448 AHDraft
  • Installation026-D9 · V0⁦10%⁩Eng. Bandar M. Al-ShammariIn 123 days2027-02-2821 Ramadan 1448 AHDraft
  • Testing & commissioning026-D10 · V0⁦10%⁩Sarah A. Al-QarniIn 163 days2027-04-092 Dhuʻl-Qiʻdah 1448 AHDraft
  • Provisional acceptance026-D11 · V0⁦7%⁩Eng. Bandar M. Al-ShammariIn 204 days2027-05-2014 Dhuʻl-Hijjah 1448 AHDraft
  • Final acceptance026-D12 · V0⁦7%⁩Sarah A. Al-QarniIn 245 days2027-06-3025 Muharram 1449 AHDraft

Team, contracts & documents

Team

2 members

Eng. Mishari K. Al-Otaibi · Director, Sustainability & Social ResponsibilityMazen A. Al-Hazmi · Procurement & Tendering Specialist
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityProject manager (on hold)P-028m.alotaibi@chamber.sa⁦15%⁩
  • Mazen A. Al-HazmiMazen A. Al-HazmiProcurement & Tendering SpecialistESCO tenderP-038m.alhazmi@chamber.sa⁦20%⁩

Contracts

0 contracts

  • No external contracts — delivered in-house

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close