Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+123⁩ days vs approved

Baseline (original = approved)⁦2027-06-30⁩
Current forecast⁦2027-10-31⁩
By earned schedule⁦2030-05-22⁩
Critical activities
11
of ⁦14⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.15
earned ÷ planned value
Next milestone
in 80 days
Designs approved
Expand allCollapse all
Activity
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)Planned: ⁦2026-02-01⁩ → ⁦2027-06-30⁩Forecast: ⁦2026-02-01⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-02-01⁩ → ⁦2026-05-18⁩Actual: ⁦2026-02-01⁩ → ⁦2026-10-26⁩
Project plan & baselinePlanned: ⁦2026-02-01⁩ → ⁦2026-04-07⁩Actual: ⁦2026-02-01⁩ → ⁦2026-07-17⁩
Monitoring & reportingPlanned: ⁦2026-03-14⁩ → ⁦2026-05-18⁩Actual: ⁦2026-05-16⁩ → ⁦2026-10-26⁩
Project plan approvedPlanned: ⁦2026-05-18⁩ → ⁦2026-05-18⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Project plan approved
Design & permitsPlanned: ⁦2026-04-24⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-04-24⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Detailed designPlanned: ⁦2026-04-24⁩ → ⁦2026-06-28⁩Forecast: ⁦2026-04-24⁩ → ⁦2026-12-11⁩Float: ⁦0⁩dDrag to change its duration+166
Permits & approvalsPlanned: ⁦2026-06-03⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-11-19⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its dates+161
Designs approvedPlanned: ⁦2026-08-08⁩ → ⁦2026-08-08⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦288⁩dDrag to change its datesDesigns approved
Civil worksPlanned: ⁦2026-07-14⁩ → ⁦2026-12-08⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-05-04⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-07-14⁩ → ⁦2026-09-17⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-02-21⁩Float: ⁦0⁩dDrag to change its dates+157
StructurePlanned: ⁦2026-08-24⁩ → ⁦2026-10-28⁩Forecast: ⁦2027-01-30⁩ → ⁦2027-03-29⁩Float: ⁦0⁩dDrag to change its dates+152
FinishesPlanned: ⁦2026-10-04⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-03-07⁩ → ⁦2027-05-04⁩Float: ⁦0⁩dDrag to change its dates+147
Build completePlanned: ⁦2026-12-08⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-05-04⁩ → ⁦2027-05-04⁩Float: ⁦180⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-11-14⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-08-20⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-11-14⁩ → ⁦2027-01-18⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-06-09⁩Float: ⁦0⁩dDrag to change its dates+142
InstallationPlanned: ⁦2026-12-24⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-05-18⁩ → ⁦2027-07-15⁩Float: ⁦0⁩dDrag to change its dates+137
Testing & commissioningPlanned: ⁦2027-02-03⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-06-23⁩ → ⁦2027-08-20⁩Float: ⁦0⁩dDrag to change its dates+133
Testing & acceptance completePlanned: ⁦2027-04-09⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-08-20⁩ → ⁦2027-08-20⁩Float: ⁦72⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2027-03-16⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2027-03-16⁩ → ⁦2027-05-20⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-09-25⁩Float: ⁦0⁩dDrag to change its dates+128
Final acceptancePlanned: ⁦2027-04-26⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-09-03⁩ → ⁦2027-10-31⁩Float: ⁦0⁩dDrag to change its dates+123
Final handoverPlanned: ⁦2027-06-30⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-10-31⁩ → ⁦2027-10-31⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦14⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Detailed design” needs a pace ⁦8.6⁩× faster than it has kept

It earned ⁦33%⁩ in 187 days; the forecast assumes the rest in 44 days. At the pace so far it finishes on ⁦2027-11-12⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 156 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

161
161
147
G1G2G3

The critical chain

In date order, to final acceptance