PRJ-2026-026On hold3PlanningWaterfallStopped
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)
Add to watchlistHVAC and lighting retrofit on energy-performance contracts; on hold pending funding.
Project managerEng. Mishari K. Al-OtaibiProject sponsorSarah A. Al-QarniProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 1.7M
Actual cost
SAR 132K
8% of budget
Progress
8%Awaiting acceptance 6%
Estimate at completion
SAR 1.7M
SPI · CPI
0.89Schedule performance index · 0.891.00Cost performance index · 1.00
Forecast finish
2027-10-31
123 days behind baseline
PlanningStage 3 of 5
Next gate:Execution24 April 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started