PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Electronic forms

The project’s twelve forms with their status and approval path, each printable with its approval log.

Forms

8

In approval

1

Past their limit

0

Escalated automatically

0

Approved

7

1RC-PMO-F01Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

ApprovedV2 · ⁦2025-07-06⁩

2RC-PMO-F02Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

ApprovedV4 · ⁦2025-08-30⁩

3RC-PMO-F03Approval

Project weight

The weight and the relative weight in the portfolio

ApprovedV2 · ⁦2026-09-16⁩

4RC-PMO-F04Initiation

Project charter

Objective, scope, deliverables, roles and budget

ApprovedV2 · ⁦2026-01-30⁩

5RC-PMO-F05Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

In approvalV1 · ⁦2026-02-26⁩
Technical acceptanceEng. Bandar M. Al-Shammari2 working days leftWithin the time limit · Limit 3 working days

6RC-PMO-F06Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Not yet · Opens at the «Planning» stage

7RC-PMO-F07Execution

Periodic update card

Progress, status, risks and support requested

Not yet · Opens at the «Execution» stage

9RC-PMO-F09Execution

Change request

The change, its impact analysis and the approval decision

Not yet · Opens at the «Execution» stage

10RC-PMO-F10Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

ApprovedV1 · ⁦2026-09-21⁩

11RC-PMO-F11Execution

Corrective plan

Actions, owners, dates and status

Not yet · Opens at the «Execution» stage

12RC-PMO-F12Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Not yet · Opens at the «Closure» stage