Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work1.6M⁦17⁩ elements
Unallocated contingency49.5KSAR 83K
Budget at completion1.7MPRJ-2026-026
Weighted progress⁦8%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project637⁦2026-02-01⁩⁦2027-10-31⁩⁦8%⁩1.600.13—
1
Phase267⁦2026-02-01⁩⁦2026-10-26⁩⁦100%⁩0.100.10—
1.1
WBS element166⁦2026-02-01⁩⁦2026-07-17⁩⁦100%⁩0.050.050 / 1
1.2
WBS element163⁦2026-05-16⁩⁦2026-10-26⁩⁦100%⁩0.050.051 / 2
2
Phase267⁦2026-04-24⁩⁦2027-01-16⁩⁦17%⁩0.190.03—
2.1
WBS element231⁦2026-04-24⁩⁦2026-12-11⁩⁦33%⁩0.100.031 / 1
2.2
WBS element58⁦2026-11-19⁩⁦2027-01-16⁩⁦0%⁩0.10—1 / 2
3
Phase130⁦2026-12-25⁩⁦2027-05-04⁩⁦0%⁩0.61——
3.1
WBS element58⁦2026-12-25⁩⁦2027-02-21⁩⁦0%⁩0.20—1 / 1
3.2
WBS element58⁦2027-01-30⁩⁦2027-03-29⁩⁦0%⁩0.20—1 / 1
3.3
WBS element58⁦2027-03-07⁩⁦2027-05-04⁩⁦0%⁩0.20—1 / 2
4
Phase130⁦2027-04-12⁩⁦2027-08-20⁩⁦0%⁩0.48——
4.1
WBS element58⁦2027-04-12⁩⁦2027-06-09⁩⁦0%⁩0.16—1 / 1
4.2
WBS element58⁦2027-05-18⁩⁦2027-07-15⁩⁦0%⁩0.16—1 / 1
4.3
WBS element58⁦2027-06-23⁩⁦2027-08-20⁩⁦0%⁩0.16—1 / 2
5
Phase94⁦2027-07-29⁩⁦2027-10-31⁩⁦0%⁩0.22——
5.1
WBS element58⁦2027-07-29⁩⁦2027-09-25⁩⁦0%⁩0.11—1 / 1
5.2
WBS element58⁦2027-09-03⁩⁦2027-10-31⁩⁦0%⁩0.11—1 / 1
Total⁦8%⁩1.600.13
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close