PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-07-06⁩
Hijri
11 Muharram 1447 AH
ApprovedDMD-2026-026Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1The proposalAuto-filled

TitleAuto-filled
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)
Proposed byAuto-filled
Eng. Mishari K. Al-Otaibi
DepartmentAuto-filled
Sustainability & Social Responsibility Department
Submitted onAuto-filled
⁦2025-07-06⁩
Proposal numberAuto-filled
DMD-2026-026

2Justification

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

3Objectives

  1. Financial sustainability

Strategic objectives served

  • SO-4.1 — Financial sustainability

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 1.7M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 1.2M
Supervision & consultingSAR 225K
Internal teamSAR 150K
Contingency reserve (5%)SAR 85K
TotalSAR 1.7M

6Initial risks

RiskLevelProposed response
Funding left out of the 2027 budget, keeping the tender suspendedHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilitySubmitted—⁦2025-07-06⁩ 10:13
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-07-08⁩ 14:23
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-07-09⁩ 09:30
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-07-13⁩ 10:37
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2025-07-16⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-07-17⁩ 10:49
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-07-23⁩ 12:51

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-07-08⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-07-09⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2025-07-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-07-17⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-07-23⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-07-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-07-08⁩ at ⁦14:23⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-07-09⁩ at ⁦09:30⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-07-13⁩ at ⁦10:37⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-07-17⁩ at ⁦10:49⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-07-23⁩ at ⁦12:51⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-07-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-07-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Mishari K. Al-Otaibi