Execution
Suspension, resumption & cancellation
The decision, the rationale and the approvals
- Form no.
- RC-PMO-F10
- Template edition
- 1.0
- Version
- V1
- Form date
- 2026-09-21
- Hijri
- 10 Rabiʻ II 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-026
- Project
- Energy Retrofit of the Chamber’s Existing Buildings (ESCO)
- Portfolio
- Building Rehabilitation & Sustainability Portfolio
- Sector
- Support Services Sector
- Sponsor
- Sarah A. Al-Qarni
- Project manager
- Eng. Mishari K. Al-Otaibi
1The decision asked for
- Action
- Suspension
- Status nowAuto-filled
- Active
- Status afterAuto-filled
- Suspended
- Requested onAuto-filled
- 2026-09-21
- Planned resumption
- 2027-01-15
- Length of the suspensionAuto-filled
- 116 days
2Rationale
Waiting for 2027 funding of the performance contracts with the energy service companies.
3Effect on the projectAuto-filled
Approved budget
SAR 1.7M
Committed
SAR 155K
Actual
SAR 132K
Progress
8%
A suspended project keeps its stage and resumes in it; its progress is frozen in the portfolio’s progress while suspended.
Approval logChain: Suspension, resumption & cancellation · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social Responsibility | Submitted | — | 2026-09-21 11:38 |
| 2 | PMO opinion | Methodology review | Dr. Noura M. Al-OtaibiPMO — director | Approved | — | 2026-09-22 09:06 |
| 3 | Project Approval Committee | Technical acceptance | Dr. Noura M. Al-OtaibiProject Approval Committee | Approved | — | 2026-09-24 12:00 |
| 4 | Effect on financial commitments | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2026-09-24 13:28 |
| 5 | Sponsor’s decision | Technical acceptance | Sarah A. Al-QarniProject sponsor | Approved | — | 2026-09-27 12:27 |
Signatures
PMO opinion
Dr. Noura M. Al-Otaibi
Approved2026-09-22
Effect on financial commitments
Munirah A. Al-Khalidi
Approved2026-09-24
Sponsor’s decision
Sarah A. Al-Qarni
Approved2026-09-27
Project Approval Committee
Dr. Noura M. Al-Otaibi
Approved2026-09-24