PRJ-2026-026On hold3PlanningWaterfallStopped

Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofit on energy-performance contracts; on hold pending funding.

Budget (BAC)

SAR 1.7M

Actual cost

SAR 132K

⁦8%⁩ of budget

Progress

⁦8%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.7M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution24 April 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 February 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Form no.
RC-PMO-F10
Template edition
1.0
Version
V1
Form date
⁦2026-09-21⁩
Hijri
10 Rabiʻ II 1448 AH
ApprovedSTS-026-1Suspension — Energy Retrofit of the Chamber’s Existing Buildings (ESCO)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-026
Project
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1The decision asked for

Action
Suspension
Status nowAuto-filled
Active
Status afterAuto-filled
Suspended
Requested onAuto-filled
⁦2026-09-21⁩
Planned resumption
⁦2027-01-15⁩
Length of the suspensionAuto-filled
116 days

2Rationale

Waiting for 2027 funding of the performance contracts with the energy service companies.

3Effect on the projectAuto-filled

Approved budget

SAR 1.7M

Committed

SAR 155K

Actual

SAR 132K

Progress

⁦8%⁩

A suspended project keeps its stage and resumes in it; its progress is frozen in the portfolio’s progress while suspended.

Approval logChain: Suspension, resumption & cancellation · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilitySubmitted—⁦2026-09-21⁩ 11:38
2PMO opinionMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2026-09-22⁩ 09:06
3Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2026-09-24⁩ 12:00
4Effect on financial commitmentsFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-09-24⁩ 13:28
5Sponsor’s decisionTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2026-09-27⁩ 12:27

Signatures

PMO opinion

Dr. Noura M. Al-Otaibi

Approved⁦2026-09-22⁩

Effect on financial commitments

Munirah A. Al-Khalidi

Approved⁦2026-09-24⁩

Sponsor’s decision

Sarah A. Al-Qarni

Approved⁦2026-09-27⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2026-09-24⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F10 · version V1

Suspension, resumption & cancellation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Suspension, resumption & cancellation · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2026-09-21⁩

  1. Methodology review

    PMO opinion

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2026-09-22⁩ at ⁦09:06⁩

  2. Financial approval

    Effect on financial commitments

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-09-24⁩ at ⁦13:28⁩

  3. Technical acceptance

    Sponsor’s decision

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2026-09-27⁩ at ⁦12:27⁩

  4. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    On the path because: Suspension longer than the sponsor’s authority?From the authority matrix

    Approved · ⁦2026-09-24⁩ at ⁦12:00⁩

Steps that do not apply to this record

  • Contracts suspended or resumed — the condition «Contract link?» does not hold
  • Secretary-General — the condition «Cancelling a project of SAR 5M or more?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-21⁩

    Waiting for 2027 funding of the performance contracts with the energy service companies.

    Eng. Mishari K. Al-Otaibi

Only one version so far.