Portfolio · PF-INF

New Headquarters & Investment Assets Portfolio

Off track

The new headquarters, the investment tower, the conference and exhibition hall and the entrepreneurship centre, with smart access, the network, the studio and the unified contact centre.

What-if scenarios
Approved budget
SAR 136.5M

incl. SAR 4.3M unallocated reserve

Actual spend
SAR 46.1M

⁦34%⁩ of budget

EAC
SAR 138.5M+1.5%

Estimate at completion

Expected value
SAR 210M

⁦3%⁩ realised

Health score
58−5

was ⁦63⁩ in May

Manager

Eng. Bandar M. Al-Shammari

Director General, Facilities & General Services

Owner

Sarah A. Al-Qarni

Assistant Secretary-General, Support Services

AI insight

⁦5⁩ projects in this portfolio are pulling its health down

Most of it comes from “The Chamber’s Investment Building — Business Tower on King Fahd Road” (SPI ⁦0.80⁩) and “The Chamber’s New Headquarters Building” (SPI ⁦0.82⁩). Fixing those two lifts the portfolio towards ⁦67⁩ within two quarters.

Confidence⁦81%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
The Chamber’s New Headquarters Building100.0⁦18.3%⁩⁦42%⁩⁦7.7%⁩
Chamber Conference & Exhibition Hall — Phase 189.0⁦16.3%⁩⁦2%⁩⁦0.3%⁩
The Chamber’s Investment Building — Business Tower on King Fahd Road88.0⁦16.1%⁩⁦44%⁩⁦7.1%⁩
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality80.0⁦14.6%⁩⁦33%⁩⁦4.8%⁩
Chamber Channel & Podcast Studio — with a Media Sponsor66.0⁦12.1%⁩⁦2%⁩⁦0.2%⁩
Smart Access, Visitor & Event Management at HQ & the Branches62.0⁦11.3%⁩⁦79%⁩⁦9.0%⁩
Unified Enterprise Network for HQ & the Branches62.0⁦11.3%⁩⁦55%⁩⁦6.2%⁩
Unified Contact Centre 920004565 & AI AssistantLeft out — proposed69.0—⁦0%⁩—
Portfolio progress⁦35.3%⁩

How it is computed

⁦35.3%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦1⁩
  • · For comparison: weighting by budget alone gives ⁦32.8%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

58Off track
DimensionScoreWeightPoints
Schedule48⁦20%⁩9.6
Cost70⁦20%⁩14.0
Risk36⁦15%⁩5.4
Scope66⁦10%⁩6.6
Quality72⁦10%⁩7.2
Resources56⁦10%⁩5.6
Stakeholders62⁦5%⁩3.1
Benefits65⁦10%⁩6.5
Total58

Health-score trend

May – October 2026

6358

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • At risk
  • Off track
Approved budget · SAR 59M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1The Chamber’s New Headquarters BuildingPRJ-2026-002·Priority score 90Off track
  2. 2The Chamber’s Investment Building — Business Tower on King Fahd RoadPRJ-2026-020·Priority score 86Off track
  3. 3Chamber Conference & Exhibition Hall — Phase 1PRJ-2026-021·Priority score 84On track
  4. 4Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityPRJ-2026-034·Priority score 78At risk
  5. 5Unified Enterprise Network for HQ & the BranchesPRJ-2026-018·Priority score 71At risk
  6. 6Chamber Channel & Podcast Studio — with a Media SponsorPRJ-2026-022·Priority score 69On track
  7. 7Smart Access, Visitor & Event Management at HQ & the BranchesPRJ-2026-013·Priority score 68At risk
  8. 8Unified Contact Centre 920004565 & AI AssistantPRJ-2026-024·Priority score 64On track

Portfolio priorities 2026–2027

  • Clear the groundwater block at the Business Tower on the new HQ’s critical pathDewatering on axes 12–16 is five months late, and the new HQ’s façade and MEP mock-up waits on its trial in the tower.
  • Fit out 60 committee & training halls this year48 commissioned to October.
  • Offer the Business Tower and new HQ retail space and car parks to investorsMoves non-membership revenue toward target.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 136.5MSAR 136.5M
Unallocated reserve−SAR 4.3MSAR 132.3M
New Headquarters & Investment Assets Programme+SAR 5.8MSAR 138.1M
Smart Headquarters & Communication Channels Programme+SAR 440KSAR 138.5M
Estimate at completionSAR 138.5MSAR 138.5M

Budget use

46.1M/ 136.5M2Mprojected overrun(⁦1.5%⁩)
Actual spend
46.1M
Committed
90.9M
Approved budget
136.5M
Estimate at completion
138.5M

Expected-value mix

Expected-value mix

SAR 210M

Expected value

  • Time savedSAR 79.8M⁦38%⁩
  • RevenueSAR 67.2M⁦32%⁩
  • Beneficiary satisfactionSAR 37.8M⁦18%⁩
  • Sustainability (ESG)SAR 25.2M⁦12%⁩
Expected-value mix
CategoryValueShare
Time savedSAR 79.8M⁦38%⁩
RevenueSAR 67.2M⁦32%⁩
Beneficiary satisfactionSAR 37.8M⁦18%⁩
Sustainability (ESG)SAR 25.2M⁦12%⁩
TotalSAR 210M⁦100%⁩

SAR 6.6M

Expected value SAR 210M

⁦62%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦8⁩ results
Export CSV
The Chamber’s New Headquarters BuildingPRJ-2026-002PG-074ExecutionOff track⁦42%⁩⁦18.3%⁩P1P1 · Top priority — score ⁦90⁩ of 10059M63.4M⁦+7.5%⁩0.82Schedule performance index · 0.820.93Cost performance index · 0.93Risk score · Weak
Chamber Conference & Exhibition Hall — Phase 1PRJ-2026-021PG-073PlanningOn track⁦2%⁩⁦16.3%⁩P1P1 · Top priority — score ⁦84⁩ of 10026M26M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Fair
The Chamber’s Investment Building — Business Tower on King Fahd RoadPRJ-2026-020PG-074ExecutionOff track⁦44%⁩⁦16.1%⁩P1P1 · Top priority — score ⁦86⁩ of 10017.3M18.2M⁦+5.3%⁩0.80Schedule performance index · 0.800.95Cost performance index · 0.95Risk score · Weak
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityPRJ-2026-034PG-074ExecutionAt risk⁦33%⁩⁦14.6%⁩P1P1 · Top priority — score ⁦78⁩ of 10011.9M12.4M⁦+4.2%⁩0.89Schedule performance index · 0.890.96Cost performance index · 0.96Risk score · Weak
Unified Enterprise Network for HQ & the BranchesPRJ-2026-018PG-084ExecutionAt risk⁦55%⁩⁦11.3%⁩P2P2 · High priority — score ⁦71⁩ of 1006.6M6.8M⁦+3.1%⁩0.87Schedule performance index · 0.870.97Cost performance index · 0.97Risk score · Fair
Unified Contact Centre 920004565 & AI AssistantPRJ-2026-024PG-081Pre-startOn track⁦0%⁩—P2P2 · High priority — score ⁦64⁩ of 1005.5M5.5M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Fair
Smart Access, Visitor & Event Management at HQ & the BranchesPRJ-2026-013PG-084ExecutionAt risk⁦79%⁩⁦11.3%⁩P2P2 · High priority — score ⁦68⁩ of 1003.7M3.9M⁦+6.4%⁩0.88Schedule performance index · 0.880.94Cost performance index · 0.94Risk score · Fair
Chamber Channel & Podcast Studio — with a Media SponsorPRJ-2026-022PG-083PlanningOn track⁦2%⁩⁦12.1%⁩P2P2 · High priority — score ⁦69⁩ of 1002.3M2.3M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Good
Total · 8132.3M138.5M
⁦1⁩–⁦8⁩ of ⁦8⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Open-risk heat map

13 risks

Open-risk heat map
  • Critical3
  • High3
  • Medium7
  • Low0
  • Risks 13
Probability
5
4
3
2
1
12345

Impact

Open-risk heat map
Probability \ Impact12345
50 · Low0 · Medium0 · High1 · Critical0 · Critical
40 · Low0 · Medium1 · Medium2 · High2 · Critical
30 · Low0 · Low3 · Medium2 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium1 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Latest on this portfolio

8 October 2026

  1. Approval: Bid Evaluation & Award Committee Approved DEC-2026-036Pre-qualification results approved for the conference & exhibition hall contractors

    2026-10-08 10:00

25 August 2026

  1. Approval: Strategy & Projects Steering Committee Approved DEC-2026-045Revised baseline approved for the investment building