Programme · PG-08 · New Headquarters & Investment Assets Portfolio

Smart Headquarters & Communication Channels Programme

At risk

Smart access and event management, the unified network, the channel and podcast studio, and the unified contact centre.

Approved budget
SAR 18.6M

incl. SAR 500K programme reserve

Actual spend
SAR 6.9M

⁦37%⁩ of budget

EAC
SAR 18.5M+2.4%

Estimate at completion

Progress
⁦44%⁩

Planned ⁦51%⁩

Schedule performance index
0.90

Cost performance index 0.97

Manager

Eng. Omar H. Bawazir

Director, IT Infrastructure

Sponsor

Eng. Majed S. Al-Rasheed

Executive Director, Digital Transformation & IT

Projects

4 projects

2025-02-16 — 2028-12-31

On track 2At risk 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    A unified contact centre on 920004565 and an AI assistant answering members around the clock

  2. 2

    Cut member and visitor entry time at HQ, the branches and events by 45% with smart gates

  3. 3

    HQ and every chamber branch on the secure enterprise network

Programme benefits

From baseline to target

  • Entry time reduction at HQ and the branches

    by ⁦2027⁩
    Baseline 0Current 22 %Target 45
  • HQ and branches on the secure network

    by ⁦2027⁩
    Baseline 35Current 64 %Target 100

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2025202620272028
2026-12-15
2027-03-05
2028-03-31
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Cameras and smart gates at HQ and the branches connect over the secure enterprise network

  • Critical

    The channel and podcast studio needs high-capacity network links for live broadcast

  • The contact centre plays the service video guides recorded in the studio

  • Appointments and smart access are run from the unified contact centre

Shared risks

Risks that hit more than one project, managed at programme level.

12

Excavation permits for fibre to the branches delay the network and everything on it

PRK-08-1·Mitigate·Eng. Omar H. Bawazir

Affects

Open risks in the programme’s projects

5 risks

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium5
  • Low0
  • Risks 5
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium1 · Medium0 · High0 · Critical
30 · Low0 · Low3 · Medium1 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Eng. Majed S. Al-RasheedManage closelyEng. Omar H. BawazirManage closelyNawaf S. Al-AjmiManage closelyEng. Yasser M. Al-ZahraniManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

    Committees

    Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & IT
    Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
    Project Approval Committee

    Fortnightly · Quorum ⁦4⁩

    Faisal A. Al-Shehri · Director General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceDr. Amal F. Al-Sudairi · Director General, Strategy & the PMOTariq S. Al-Yami · Head, Institutional Performance & Quality
    Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

    Programme projects

    The programme’s performance is computed from these projects.

    ⁦4⁩ results
    Export CSV
    Manager
    Smart Access, Visitor & Event Management at HQ & the BranchesPRJ-2026-013Eng. Waleed O. Al-Juhani4ExecutionAt risk⁦79%⁩3.7M3.9M⁦+6.4%⁩0.88Schedule performance index · 0.880.94Cost performance index · 0.94
    Unified Enterprise Network for HQ & the BranchesPRJ-2026-018Eng. Omar H. Bawazir4ExecutionAt risk⁦55%⁩6.6M6.8M⁦+3.1%⁩0.87Schedule performance index · 0.870.97Cost performance index · 0.97
    Chamber Channel & Podcast Studio — with a Media SponsorPRJ-2026-022Rami Al-Khatib3PlanningOn track⁦2%⁩2.3M2.3M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
    Unified Contact Centre 920004565 & AI AssistantPRJ-2026-024Eng. Omar H. Bawazir1Pre-startOn track⁦0%⁩5.5M5.5M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
    Total · 418.1M18.5M
    ⁦1⁩–⁦4⁩ of ⁦4⁩

    Budget shares

    Budget shares

    SAR 18.1M

    Budget

    • Smart Access, Visitor & Event Management at HQ & the BranchesSAR 3.7M⁦20%⁩
    • Unified Enterprise Network for HQ & the BranchesSAR 6.6M⁦36%⁩
    • Chamber Channel & Podcast Studio — with a Media SponsorSAR 2.3M⁦13%⁩
    • Unified Contact Centre 920004565 & AI AssistantSAR 5.5M⁦30%⁩
    Budget shares
    CategoryValueShare
    Smart Access, Visitor & Event Management at HQ & the BranchesSAR 3.7M⁦20%⁩
    Unified Enterprise Network for HQ & the BranchesSAR 6.6M⁦36%⁩
    Chamber Channel & Podcast Studio — with a Media SponsorSAR 2.3M⁦13%⁩
    Unified Contact Centre 920004565 & AI AssistantSAR 5.5M⁦30%⁩
    TotalSAR 18.1M⁦100%⁩