Late groundwater treatment at the Business Tower and late handover of the new HQ site
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Programme · PG-07 · New Headquarters & Investment Assets Portfolio
The new headquarters, the investment tower, the conference and exhibition hall and the entrepreneurship centre.
incl. SAR 2M programme reserve
34% of budget
Estimate at completion
Planned 37%
Cost performance index 0.95
Manager
Eng. Ahmed Y. Asiri
Director, Construction Projects & Buildings
Sponsor
Eng. Bandar M. Al-Shammari
Director General, Facilities & General Services
Projects
4 projects
2024-03-03 — 2028-12-31
On track 1At risk 1Off track 2
What the programme must achieve, and the strategic objectives it serves.
A new chamber-owned headquarters in north Riyadh with a hall for conferences and the General Assembly
Investment assets — the Business Tower and the conference & exhibition hall — that lift non-membership revenue
An entrepreneurship centre and co-working spaces with the Riyadh Region Municipality
From baseline to target
Committee & training halls fitted out this year
by 2026Members within 30 minutes of a branch or service point
by 2027Rent avoided (cumulative to 2035)
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The façade and MEP mock-up is proven in the Business Tower before it is fixed for the new HQ
Critical
The entrepreneurship centre applies the design standards approved for the new HQ
Risks that hit more than one project, managed at programme level.
Late groundwater treatment at the Business Tower and late handover of the new HQ site
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Steel and ready-mix shortages at the peak of the season
PRK-07-2·Mitigate·Eng. Ahmed Y. Asiri
8 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 1 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 2 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Headquarters and branch projects delivered to plan
73%
+1
Target 85%86%
Non-membership revenue from services, programmes and events (cumulative)
52.4SAR M
+6
Target 64.082%
Committee and training halls fitted out this year (cumulative)
48halls
+4
Target 6080%
Attendee satisfaction with forums and events
84%
0
Target 88%95%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely5
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| The Chamber’s New Headquarters BuildingPRJ-2026-002 | Eng. Ahmed Y. Asiri | 4Execution | Off track | 42% | 59M | 63.4M+7.5% | 0.82Schedule performance index · 0.82 | 0.93Cost performance index · 0.93 |
| The Chamber’s Investment Building — Business Tower on King Fahd RoadPRJ-2026-020 | Eng. Ahmed Y. Asiri | 4Execution | Off track | 44% | 17.3M | 18.2M+5.3% | 0.80Schedule performance index · 0.80 | 0.95Cost performance index · 0.95 |
| Chamber Conference & Exhibition Hall — Phase 1PRJ-2026-021 | Eng. Ibrahim A. Al-Ghamdi | 3Planning | On track | 2% | 26M | 26M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityPRJ-2026-034 | Eng. Ibrahim A. Al-Ghamdi | 4Execution | At risk | 33% | 11.9M | 12.4M+4.2% | 0.89Schedule performance index · 0.89 | 0.96Cost performance index · 0.96 |
| Total · 4 | 114.2M | 120M |
SAR 114.2M
Budget
| Category | Value | Share |
|---|---|---|
| The Chamber’s New Headquarters Building | SAR 59M | 52% |
| The Chamber’s Investment Building — Business Tower on King Fahd Road | SAR 17.3M | 15% |
| Chamber Conference & Exhibition Hall — Phase 1 | SAR 26M | 23% |
| Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality | SAR 11.9M | 10% |
| Total | SAR 114.2M | 100% |