The Riyadh Region stretches from Shaqra to Wadi Al-Dawasir; members in the governorates and industrial cities deserve the same service within thirty minutes, and the new HQ ends the crowding at the current one.
The objective’s weakest KPI, “Committee and training halls fitted out this year (cumulative)”, is at 80% of its target, and its heaviest project, “The Chamber’s New Headquarters Building”, is Off track. Fixing that one path lifts the objective more than any other action.
This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.
Approved in plan version 1.1Board resolution BRD-1447-092026-03-25·6 Shawwal 1447 AH
No change requests on this item since the plan was approved.
Corrective actions
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the handover of the new HQ site’s northern plot with the Riyadh Region Municipality and the Saudi Electricity Company
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013·b.alshammari@chamber.saDue 2026-10-208 days overdue2026-10-20·9 Jumada I 1448 AHK-2.3.1The Chamber’s New Headquarters Building
Overdue
Take the conference & general-assembly hall fit-out out of the new HQ construction contract and tender it separately
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020·a.asiri@chamber.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHK-2.3.1The Chamber’s New Headquarters Building
In progress
An extra evening shift on the committee-rooms wing at the current HQ until year end