SO-2.3 · The chamber’s services across Riyadh city and its governorates

New headquarters & investment assets

Off trackDelivered wholly through projectsA Partner in Growth

The chamber’s new headquarters in north Riyadh, the investment building on King Fahd Road and the chamber conference & exhibition hall.

⁦43%⁩

Initiative weighted progress

⁦42.6%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦42.6%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦85%⁩

⁦15⁩ points short of 100%

Primary projects’ budget

102.3M

3 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
The Chamber’s New Headquarters Building

PRJ-2026-002

Primary⁦60%⁩⁦42%⁩⁦25.2%⁩
The Chamber’s Investment Building — Business Tower on King Fahd Road

PRJ-2026-020

Primary⁦25%⁩⁦44%⁩⁦11.0%⁩
Chamber Conference & Exhibition Hall — Phase 1

PRJ-2026-021No approved share yet

PrimaryNo share⁦2%⁩—

Linked projects’ progress

Σ (contribution × progress) = ⁦36.2%⁩ points ÷ shares counted ⁦85%⁩ = ⁦42.6%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦42.6%⁩

Shares add up to ⁦85%⁩, not 100%.A proposed or cancelled project, or one with no approved share, is left out; a suspended one follows the rule set on the project weight model.

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

The new HQ in north Riyadh with its conference & general-assembly hall, the investment building on King Fahd Road and the conference & exhibition hall — phase 1.

Outputs

  • The new headquarters
  • The Business Tower
  • The conference & exhibition hall

Delivery phases

  • Headquarters

    2024-03-03 — 2027-09-12

  • Business Tower

    2024-06-02 — 2027-08-03

  • Conference & exhibition hall

    2026-04-05 — 2028-12-31

Today · ⁦2026-10-28⁩

Awaiting approval

Share proposals strategy management has not approved yet; they do not count until approved

  • Chamber Conference & Exhibition Hall — Phase 1None⁦15%⁩

    Set the conference & exhibition hall’s share now its charter is approved; it brings the initiative to 100 %

    Proposed by Eng. Ahmed Y. Asiri · ⁦2026-10-22⁩

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

No benefits registered for these projects yet; they are recorded at closure and handover.

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: The Chamber’s New Headquarters Building

1Deliverable weight in the project

⁦38.0%⁩

Weight of «Civil works» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦18.3%⁩

Its relative weight in New Headquarters & Investment Assets Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦60%⁩

Its contribution to «New headquarters & investment assets»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayHighOpen

    The HQ site’s northern plot handed over late

    Response: Escalate to the Riyadh Region Municipality and resequence zones 3 and 4

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa
  • Possible riskHighBeing treated

    Groundwater at the Business Tower site raising foundation cost

    Response: Permanent dewatering and a foundation redesign within the contingency

    Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa

Deviation

Budget: projects total SAR 102.3M against the estimate SAR 100M

Schedule: last project ends ⁦2028-12-31⁩ against the initiative end ⁦2028-12-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Board resolution BRD-1447-092026-03-256 Shawwal 1447 AH

No change requests on this item since the plan was approved.