The project with the most weight on this KPI is “The Chamber’s New Headquarters Building”, with 58% of the linked budget, and it is Off track. Speeding it up is the fastest way to close the gap before December.
This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.
Approved in plan version 1.1Board resolution BRD-1447-092026-03-25·6 Shawwal 1447 AH
No change requests on this item since the plan was approved.
Corrective actions
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the handover of the new HQ site’s northern plot with the Riyadh Region Municipality and the Saudi Electricity Company
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013·b.alshammari@chamber.saDue 2026-10-208 days overdue2026-10-20·9 Jumada I 1448 AHThe Chamber’s New Headquarters Building
Overdue
Take the conference & general-assembly hall fit-out out of the new HQ construction contract and tender it separately
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020·a.asiri@chamber.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHThe Chamber’s New Headquarters Building
In progress