PRJ-2026-033On hold3PlanningConstructionStopped

Wadi Al-Dawasir Branch Building

Add to watchlist

On hold pending land allocation and the title deed from the owning entity.

Budget (BAC)

SAR 10.5M

Actual cost

SAR 210K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−14

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2% done against 2% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.3The chamber’s services across Riyadh city and its governorates

Main initiative

Under no initiative — listed under «projects with no strategic link»

Secondary links

No secondary links

Annual work-plan line
WP-2026-033
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦2%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦98%⁩

1 deliverable accepted

  • Project plan & baseline⁦2%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦2⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    210K/ 10.5M
    Actual spend
    210K
    Committed
    230K
    Approved budget
    10.5M
    Estimate at completion
    10.5M

    Next milestones

    • 50% of works complete⁦2027-08-10⁩was ⁦2027-05-10⁩Late
    • Provisional acceptance⁦2028-09-08⁩was ⁦2028-04-23⁩Late
    • Closure⁦2028-12-31⁩was ⁦2028-06-30⁩Late

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    1 open risk, exposure SAR 600K

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0044Late land allocation and title deed from the owning entity in Wadi Al-DawasirProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical1
    • High0
    • Medium0
    • Low0

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦12⁩ approved

    • Project plan & baseline033-D1 · V1 · CRT-033-01⁦2%⁩Eng. Shahad M. Al-Malki⁦2026-06-17⁩2026-06-172 Muharram 1448 AHApproved
    • Monitoring & reporting033-D2 · V0⁦3%⁩Eng. Bandar M. Al-Shammari65 days overdue2026-08-2411 Rabiʻ I 1448 AHDraft
    • Detailed design033-D3 · V0⁦6%⁩Eng. Bandar M. Al-ShammariIn 2 days2026-10-3019 Jumada I 1448 AHDraft
    • Permits & approvals033-D4 · V0⁦6%⁩Eng. Sami A. Al-FraihIn 70 days2027-01-0628 Rajab 1448 AHDraft
    • Site works & excavation033-D5 · V0⁦13%⁩Eng. Sami A. Al-FraihIn 138 days2027-03-157 Shawwal 1448 AHDraft
    • Structure033-D6 · V0⁦13%⁩Eng. Shahad M. Al-MalkiIn 205 days2027-05-2115 Dhuʻl-Hijjah 1448 AHDraft
    • Finishes033-D7 · V0⁦13%⁩Eng. Bandar M. Al-ShammariIn 273 days2027-07-2824 Safar 1449 AHDraft
    • Supply033-D8 · V0⁦10%⁩Eng. Shahad M. Al-MalkiIn 341 days2027-10-044 Jumada I 1449 AHDraft
    • Installation033-D9 · V0⁦10%⁩Eng. Bandar M. Al-ShammariIn 408 days2027-12-1012 Rajab 1449 AHDraft
    • Testing & commissioning033-D10 · V0⁦10%⁩Eng. Sami A. Al-FraihIn 476 days2028-02-1620 Ramadan 1449 AHDraft
    • Provisional acceptance033-D11 · V0⁦7%⁩Eng. Bandar M. Al-ShammariIn 543 days2028-04-2328 Dhuʻl-Qiʻdah 1449 AHDraft
    • Final acceptance033-D12 · V0⁦7%⁩Eng. Sami A. Al-FraihIn 611 days2028-06-307 Safar 1450 AHDraft

    Team, contracts & documents

    Team

    1 member

    Eng. Shahad M. Al-Malki · Senior Project Manager — Buildings & Facilities
    • Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesProject manager (on hold)P-022s.almalki@chamber.sa⁦10%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled