Late land allocation and handover stalls the exit from leased premises
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
Programme · PG-05 · Branches, Service & Training Centres Portfolio
The Training & Employment Centre complex and the Wadi Al-Dawasir branch instead of leased premises.
incl. SAR 900K programme reserve
52% of budget
Estimate at completion
Planned 45%
Cost performance index 0.86
Manager
Eng. Shahad M. Al-Malki
Senior Project Manager — Buildings & Facilities
Sponsor
Sarah A. Al-Qarni
Assistant Secretary-General, Support Services
Projects
2 projects
2024-02-04 — 2028-12-31
Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
End the leased training venues in Riyadh by 2028 with the Training & Employment Centre complex
A permanent, chamber-owned home for the Wadi Al-Dawasir branch
Bring training halls and job fairs together in owned buildings with one point of access for trainees
From baseline to target
Annual lease savings
by 2028Training halls moved into owned buildings
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Wadi Al-Dawasir branch uses the standard training-hall design approved for the training centre complex
Risks that hit more than one project, managed at programme level.
Late land allocation and handover stalls the exit from leased premises
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 2 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Members within 30 minutes of a branch or service point
76.4%
+1
Target 78.0%98%
Trainees on the training centre’s programmes (cumulative)
1,810trainees
+230
Target 2,40075%
Savings from spend rationalisation
3.1SAR M
0
Target 4.372%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Wadi Al-Dawasir branch suspended pending land allocation
Project Approval Committee · 2026-10-22 · DEC-2026-041
Training complex extension decision deferred pending the independent engineer
Change Committee · 2026-10-21 · DEC-2026-040
Training complex contractor’s claims referred to the dispute board
Strategy & Projects Steering Committee · 2026-10-13 · DEC-2026-037
Temporary training building dropped in favour of the training complex
Executive Committee · 2026-09-08 · DEC-2026-044
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Training & Employment Centre ComplexPRJ-2026-007 | Eng. Shahad M. Al-Malki | 4Execution | Critical | 57% | 32M | 39M+21.9% | 0.70Schedule performance index · 0.70 | 0.82Cost performance index · 0.82 |
| Wadi Al-Dawasir Branch BuildingPRJ-2026-033 | Eng. Shahad M. Al-Malki | 3Planning | On hold | 2% | 10.5M | 10.5M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 2 | 42.5M | 49.5M |
SAR 42.5M
Budget
| Category | Value | Share |
|---|---|---|
| Training & Employment Centre Complex | SAR 32M | 75% |
| Wadi Al-Dawasir Branch Building | SAR 10.5M | 25% |
| Total | SAR 42.5M | 100% |