Programme · PG-05 · Branches, Service & Training Centres Portfolio

Chamber-owned Premises Programme

Critical

The Training & Employment Centre complex and the Wadi Al-Dawasir branch instead of leased premises.

Approved budget
SAR 43.4M

incl. SAR 900K programme reserve

Actual spend
SAR 22.5M

⁦52%⁩ of budget

EAC
SAR 49.5M+16.5%

Estimate at completion

Progress
⁦31%⁩

Planned ⁦45%⁩

Schedule performance index
0.77

Cost performance index 0.86

Manager

Eng. Shahad M. Al-Malki

Senior Project Manager — Buildings & Facilities

Sponsor

Sarah A. Al-Qarni

Assistant Secretary-General, Support Services

Projects

2 projects

2024-02-04 — 2028-12-31

Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    End the leased training venues in Riyadh by 2028 with the Training & Employment Centre complex

  2. 2

    A permanent, chamber-owned home for the Wadi Al-Dawasir branch

  3. 3

    Bring training halls and job fairs together in owned buildings with one point of access for trainees

Programme benefits

From baseline to target

  • Annual lease savings

    by ⁦2028⁩
    Baseline 0Current 0 SAR MTarget 3.2
  • Training halls moved into owned buildings

    by ⁦2028⁩
    Baseline 0Current 0 hallsTarget 14

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-06-01
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The Wadi Al-Dawasir branch uses the standard training-hall design approved for the training centre complex

Shared risks

Risks that hit more than one project, managed at programme level.

25

Late land allocation and handover stalls the exit from leased premises

PRK-05-1·Escalate·Eng. Shahad M. Al-Malki

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical2
  • High2
  • Medium0
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High2 · Critical0 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium0 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Sarah A. Al-QarniManage closelyEng. Turki A. Al-AnaziManage closelyEng. Ibrahim A. Al-GhamdiManage closelyMunirah A. Al-KhalidiManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & IT
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & ITSarah A. Al-Qarni · Assistant Secretary-General, Support Services
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Change Committee

Weekly · Quorum ⁦4⁩

Dr. Noura M. Al-Otaibi · Director, Project Management OfficeKhalid N. Al-Mutairi · Senior Finance & Procurement SpecialistMunirah A. Al-Khalidi · Director General, Finance & Procurement
Chair: Dr. Mohammed I. Al-SubaieNext meeting 2026-10-29

Programme projects

The programme’s performance is computed from these projects.

⁦2⁩ results
Export CSV
Manager
Training & Employment Centre ComplexPRJ-2026-007Eng. Shahad M. Al-Malki4ExecutionCritical⁦57%⁩32M39M⁦+21.9%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Wadi Al-Dawasir Branch BuildingPRJ-2026-033Eng. Shahad M. Al-Malki3PlanningOn hold⁦2%⁩10.5M10.5M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 242.5M49.5M
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SAR 42.5M

Budget

  • Training & Employment Centre ComplexSAR 32M⁦75%⁩
  • Wadi Al-Dawasir Branch BuildingSAR 10.5M⁦25%⁩
Budget shares
CategoryValueShare
Training & Employment Centre ComplexSAR 32M⁦75%⁩
Wadi Al-Dawasir Branch BuildingSAR 10.5M⁦25%⁩
TotalSAR 42.5M⁦100%⁩