Portfolio · PF-CAP

Branches, Service & Training Centres Portfolio

Off track

The Training & Employment Centre complex, the Second Industrial City branch, the new Premium Members Centre and the Wadi Al-Dawasir branch.

What-if scenarios
Approved budget
SAR 67M

incl. SAR 2.3M unallocated reserve

Actual spend
SAR 32.9M

⁦49%⁩ of budget

EAC
SAR 73.7M+9.9%

Estimate at completion

Expected value
SAR 95M

⁦1%⁩ realised

Health score
52−9

was ⁦61⁩ in May

Manager

Eng. Abdulrahman S. Al-Harbi

Director General, Training & Entrepreneurship

Owner

Eng. Sami A. Al-Fraih

Assistant Secretary-General, Member Experience & Business Development

Programmes4 projects

Chamber-owned Premises Programme⁦31%⁩Branches & Service Centres Programme⁦45%⁩
At risk 1Off track 1Critical 1On hold 1

AI insight

⁦3⁩ projects in this portfolio are pulling its health down

Most of it comes from “Training & Employment Centre Complex” (SPI ⁦0.70⁩) and “Chamber Branch & Manufacturers’ Service Centre — Second Industrial City” (SPI ⁦0.78⁩). Fixing those two lifts the portfolio towards ⁦61⁩ within two quarters.

Confidence⁦81%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
Training & Employment Centre Complex89.0⁦27.3%⁩⁦57%⁩⁦15.6%⁩
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City82.0⁦25.2%⁩⁦39%⁩⁦9.8%⁩
New Premium Members Centre & VIP Lounges80.0⁦24.5%⁩⁦52%⁩⁦12.8%⁩
Wadi Al-Dawasir Branch BuildingSuspended — progress frozen75.0⁦23.0%⁩⁦1%⁩⁦0.2%⁩
Portfolio progress⁦38.4%⁩

How it is computed

⁦38.4%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦0⁩
  • · For comparison: weighting by budget alone gives ⁦43.5%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

52Off track
DimensionScoreWeightPoints
Schedule42⁦20%⁩8.4
Cost50⁦20%⁩10.0
Risk30⁦15%⁩4.5
Scope64⁦10%⁩6.4
Quality75⁦10%⁩7.5
Resources58⁦10%⁩5.8
Stakeholders60⁦5%⁩3.0
Benefits64⁦10%⁩6.4
Total52

Health-score trend

May – October 2026

6152

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • At risk
  • Off track
  • Critical
  • On hold
Approved budget · SAR 32M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Training & Employment Centre ComplexPRJ-2026-007·Priority score 81Critical
  2. 2Chamber Branch & Manufacturers’ Service Centre — Second Industrial CityPRJ-2026-006·Priority score 79Off track
  3. 3New Premium Members Centre & VIP LoungesPRJ-2026-019·Priority score 73At risk
  4. 4Wadi Al-Dawasir Branch BuildingPRJ-2026-033·Priority score 61On hold

Portfolio priorities 2026–2027

  • Stop the schedule bleed on the Training & Employment Centre complexSPI at 0.70 and the building contractor’s claims are open before the steering committee.
  • End leased training venues by 2028The portfolio’s largest return — recurring annual lease savings.
  • Hand over the Second Industrial City branch and manufacturers’ centre before the end of 2027A commitment to the Secretary-General and the board to serve member manufacturers where they work.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 67MSAR 67M
Unallocated reserve−SAR 2.3MSAR 64.7M
Chamber-owned Premises Programme+SAR 7MSAR 71.7M
Branches & Service Centres Programme+SAR 1.9MSAR 73.7M
Estimate at completionSAR 73.7MSAR 73.7M

Budget use

32.9M/ 67M6.7Mprojected overrun(⁦9.9%⁩)
Actual spend
32.9M
Committed
50.4M
Approved budget
67M
Estimate at completion
73.7M

Expected-value mix

Expected-value mix

SAR 95M

Expected value

  • Cost savingSAR 43.7M⁦46%⁩
  • Beneficiary satisfactionSAR 28.5M⁦30%⁩
  • Sustainability (ESG)SAR 13.3M⁦14%⁩
  • RevenueSAR 9.5M⁦10%⁩
Expected-value mix
CategoryValueShare
Cost savingSAR 43.7M⁦46%⁩
Beneficiary satisfactionSAR 28.5M⁦30%⁩
Sustainability (ESG)SAR 13.3M⁦14%⁩
RevenueSAR 9.5M⁦10%⁩
TotalSAR 95M⁦100%⁩

SAR 1.1M

Expected value SAR 95M

⁦34%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦4⁩ results
Export CSV
Training & Employment Centre ComplexPRJ-2026-007PG-054ExecutionCritical⁦57%⁩⁦27.3%⁩P1P1 · Top priority — score ⁦81⁩ of 10032M39M⁦+21.9%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82Risk score · Weak
Chamber Branch & Manufacturers’ Service Centre — Second Industrial CityPRJ-2026-006PG-064ExecutionOff track⁦39%⁩⁦25.2%⁩P1P1 · Top priority — score ⁦79⁩ of 10014.3M16.1M⁦+12.4%⁩0.78Schedule performance index · 0.780.89Cost performance index · 0.89Risk score · Weak
Wadi Al-Dawasir Branch BuildingPRJ-2026-033PG-053PlanningOn hold⁦2%⁩⁦23.0%⁩P2P2 · High priority — score ⁦61⁩ of 10010.5M10.5M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Weak
New Premium Members Centre & VIP LoungesPRJ-2026-019PG-064ExecutionAt risk⁦52%⁩⁦24.5%⁩P2P2 · High priority — score ⁦73⁩ of 1007.9M8.1M⁦+2.0%⁩0.93Schedule performance index · 0.930.98Cost performance index · 0.98Risk score · Good
Total · 464.7M73.7M
⁦1⁩–⁦4⁩ of ⁦4⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Open-risk heat map

7 risks

Latest on this portfolio

Yesterday27 October 2026

  1. Approval: Bid Evaluation & Award Committee Approved DEC-2026-043Replacement bank guarantee accepted from the Second Industrial City branch contractor

    2026-10-27 10:00

22 October 2026

  1. Rejection: Project Approval Committee Hold DEC-2026-041Wadi Al-Dawasir branch suspended pending land allocation

    2026-10-22 10:00

21 October 2026

13 October 2026

  1. Approval: Strategy & Projects Steering Committee Approved DEC-2026-037Training complex contractor’s claims referred to the dispute board

    2026-10-13 10:00

8 September 2026

  1. Rejection: Executive Committee Cancel DEC-2026-044Temporary training building dropped in favour of the training complex