RSK-0039New Premium Members Centre & VIP Lounges
Late supply of audio-visual systems for the Premium Members Centre rooms
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
The VIP-lounge audio, display and video-conferencing systems are imported to a special spec and wait on the standard lounge design
Preventive controls
- An early purchase order for the long-lead equipment
- Approve the standard lounge design from the National Products branch trial without waiting for it to finish
2 / 2
Event
Late supply of audio-visual systems for the Premium Members Centre rooms
No purchase order by mid-November
Contingency
Fit two rooms with mobile kits until the systems arrive
Impact
The centre opens without ready meeting lounges; full operation about two months late
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 105K
Residual
33% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 4 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Fahad T. Al-Sulami
Currently followed up here- 2
Programme manager
Eng. Fahad T. Al-Sulami
- 3
PMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
An early purchase order for the long-lead equipment
Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saIn progressIn 18 days2026-11-155 Jumada II 1448 AHApprove the standard lounge design from the National Products branch trial without waiting for it to finish
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.saNot startedIn 34 days2026-12-0121 Jumada II 1448 AH
Trigger
No purchase order by mid-November
Contingency
Fit two rooms with mobile kits until the systems arrive