New Premium Members Centre & VIP Lounges
Add to watchlistA full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
SAR +161K
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started