PRJ-2026-019At risk4ExecutionConstructionIn progress
New Premium Members Centre & VIP Lounges
Add to watchlistA full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.
Project managerEng. Fahad T. Al-SulamiProject sponsorEng. Sami A. Al-FraihProgrammeBranches & Service Centres Programme
Budget (BAC)
SAR 7.9M
Actual cost
SAR 4.2M
53% of budget
Progress
52%Awaiting acceptance 11%
Estimate at completion
SAR 8.1M
SAR +161K
SPI · CPI
0.93Schedule performance index · 0.930.98Cost performance index · 0.98
Forecast finish
2027-03-12
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-019-2026-10 | Draft | 52% | — | 2026-10-26 |
| September 2026UPD-019-2026-09 | Approved | 49% | — | 2026-10-02 |
| August 2026UPD-019-2026-08 | Approved | 46% | — | 2026-09-02 |