PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 7.9M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 161K
EAC SAR 8.1M
Revised request SAR 7.9M
  • Actual spendSAR 4.2M
  • Committed, not spentSAR 2.4M
  • Allotted, uncommittedSAR 1.1M
  • Contingency availableSAR 237K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 7.3M
Original budgetwhen the first baseline was approved
SAR 7.9M
Approved budgetafter approved change requests
SAR 7.9M
Current budgetavailable to spend now
SAR 7.9M
Revised budgetif the pending changes are approved
SAR 7.9M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 6.6M
Contracts1 active contract
SAR 5.9M
Purchase orders⁦3⁩ orders
SAR 650K
Remaining budgetapproved less actual
SAR 3.7M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 4.2M
Accrualswork done, not yet invoiced
SAR 168K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 8.1M
ContingencySAR 158K drawn of SAR 395K
SAR 237K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 7.3M
ApprovedSAR 7.9M
Estimate at completionSAR 8.1M
Approved is SAR 630K (⁦8.7%⁩) above the estimate
The estimate at completion is SAR 791K (⁦10.9%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-12-31⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-41019
  • WBS elements⁦5⁩ elements · P-2026-019.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦10⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 158K drawn of SAR 395K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 158K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.460.480.480.48⁦−0.02⁩
2Design & permits0.920.970.970.97⁦−0.05⁩
3Civil works2.912.852.742.92⁦−0.01⁩
4MEP works2.301.530.002.43⁦−0.13⁩
5Handover1.070.710.001.14⁦−0.06⁩
Unallocated contingency0.240.000.000.12⁦+0.12⁩
Total7.906.554.198.06⁦−0.16⁩

Budget split

WBS

SAR 7.9M

Budget

  • Management & governanceSAR 459.8K⁦6%⁩
  • Design & permitsSAR 919.6K⁦12%⁩
  • Civil worksSAR 2.9M⁦37%⁩
  • MEP worksSAR 2.3M⁦29%⁩
  • HandoverSAR 1.1M⁦14%⁩
  • Unallocated contingencySAR 237K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-18⁩+445

SPI(t) ⁦0.62⁩ against the approved finish ⁦2027-02-28⁩

Planned valuePV
SAR 7.3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 4.1M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 4.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 7.9M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.08⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−3.21⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.98
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.56
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 8.1M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 3.9M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.16⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.02
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 8.1M
  • If the rest goes to planSAR 8M
  • At cost and schedule performanceSAR 11.1M
  • The PM’s bottom-up estimateSAR 8.1M
  • To stay within SAR 7.9M, cost performance on the rest must rise to ⁦1.02⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 8.1M

Variance at completion: ⁦−0.16⁩ SAR M