PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Team & roles

1 member, about ⁦0.5⁩ full-time equivalents

Leadership

1 member

  • Eng. Fahad T. Al-SulamiProject manager⁦45%⁩A

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Sami A. Al-FraihManage closelyBadr N. Al-HaqbaniManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedCoastline Contracting & Development Co.Manage closely

Interest

Project sponsor

Eng. Sami A. Al-Fraih

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-19⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Sami A. Al-FraihProject sponsorDecisions and fundingSupportiveLeadingEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa⁦2026-10-19⁩
Badr N. Al-HaqbaniProject ownerAccepts deliverables, owns benefitsLeadingEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa⁦2026-10-22⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa⁦2026-10-16⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@chamber.sa⁦2026-10-13⁩
Coastline Contracting & Development Co.Main vendorDelivers the contracted workNeutralSupportiveEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa⁦2026-10-23⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa⁦2026-09-25⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Fahad T. Al-Sulami⁦2026-11-14⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Fahad T. Al-Sulami⁦2026-11-02⁩Overdue
  • PMOData and indicator updatesWeeklyDashboardEng. Fahad T. Al-Sulami⁦2026-10-30⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Fahad T. Al-SulamiAt launch

Coming up

By date

  1. 302026-10PMODashboard · Weekly
  2. 022026-11Project ownerEmail · Fortnightly
  3. 142026-11Project sponsorMeeting · Monthly