PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work7.7M⁦17⁩ elements
Unallocated contingency237KSAR 395K
Budget at completion7.9MPRJ-2026-019
Weighted progress⁦52%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project725⁦2025-03-16⁩⁦2027-03-11⁩⁦52%⁩7.664.19—
1
Phase233⁦2025-03-16⁩⁦2025-11-04⁩⁦100%⁩0.460.48—
1.1
WBS element143⁦2025-03-16⁩⁦2025-08-06⁩⁦100%⁩0.230.240 / 1
1.2
WBS element143⁦2025-06-14⁩⁦2025-11-04⁩⁦100%⁩0.230.241 / 2
2
Phase233⁦2025-09-11⁩⁦2026-05-02⁩⁦100%⁩0.920.97—
2.1
WBS element143⁦2025-09-11⁩⁦2026-02-01⁩⁦100%⁩0.460.481 / 1
2.2
WBS element143⁦2025-12-10⁩⁦2026-05-02⁩⁦100%⁩0.460.481 / 2
3
Phase280⁦2026-02-19⁩⁦2026-11-26⁩⁦89%⁩2.912.74—
3.1
WBS element143⁦2026-03-09⁩⁦2026-07-30⁩⁦100%⁩0.971.021 / 1
3.2
WBS element141⁦2026-06-07⁩⁦2026-10-26⁩⁦100%⁩0.971.021 / 1
3.3
WBS element280⁦2026-02-19⁩⁦2026-11-26⁩⁦68%⁩0.970.701 / 2
4
Phase76⁦2026-11-13⁩⁦2027-01-28⁩⁦0%⁩2.30——
4.1
WBS element34⁦2026-11-13⁩⁦2026-12-17⁩⁦0%⁩0.77—1 / 1
4.2
WBS element34⁦2026-12-04⁩⁦2027-01-07⁩⁦0%⁩0.77—1 / 1
4.3
WBS element34⁦2026-12-25⁩⁦2027-01-28⁩⁦0%⁩0.77—1 / 2
5
Phase55⁦2027-01-15⁩⁦2027-03-11⁩⁦0%⁩1.07——
5.1
WBS element34⁦2027-01-15⁩⁦2027-02-18⁩⁦0%⁩0.54—1 / 1
5.2
WBS element34⁦2027-02-05⁩⁦2027-03-11⁩⁦0%⁩0.54—1 / 1
Total⁦52%⁩7.664.19