RSK-0027Training & Employment Centre Complex

Late delivery of curtain-wall glazing from the overseas factory

16HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Overlapping critical activities that depend on outside supplies and approvals

Preventive controls

  • Re-sequence critical activities and refresh the critical path
  • Weekly supply follow-up with the vendor or contractor

2 / 2

Event

Late delivery of curtain-wall glazing from the overseas factory

16HighTrigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works

Impact

Key milestones slip and indirect costs rise

SAR 750K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 750K

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 3 days ago

  1. Project manager

    Current level

    Eng. Shahad M. Al-Malki

    Currently followed up here
  2. 2

    Programme manager

    Eng. Shahad M. Al-Malki

    Automatically at 15 days unreviewed · in 12 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 17 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Re-sequence critical activities and refresh the critical path

    Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa
    In progressIn 48 days2026-12-156 Rajab 1448 AH
  • Weekly supply follow-up with the vendor or contractor

    Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa
    Not startedIn 48 days2026-12-156 Rajab 1448 AH

Trigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works