Training & Employment Centre Complex
Remove from watchlistA 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +7M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started