PRJ-2026-007Critical4ExecutionConstructionStalled

Training & Employment Centre Complex

Remove from watchlist

A 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 32M

Actual cost

SAR 22.2M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 39M

SAR +7M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 32M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 7M
EAC SAR 39M
Revised request SAR 32M
  • Actual spendSAR 22.2M
  • Committed, not spentSAR 8.7M
  • Allotted, uncommittedSAR 140K
  • Contingency availableSAR 960K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 28.8M
Original budgetwhen the first baseline was approved
SAR 32M
Approved budgetafter approved change requests
SAR 32M
Current budgetavailable to spend now
SAR 32M
Revised budgetif the pending changes are approved
SAR 32M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 30.9M
Contracts2 active contracts
SAR 30.2M
Purchase orders⁦3⁩ orders
SAR 725K
Remaining budgetapproved less actual
SAR 9.8M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 22.2M
Accrualswork done, not yet invoiced
SAR 890K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 39M
ContingencySAR 640K drawn of SAR 1.6M
SAR 960K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 28.8M
ApprovedSAR 32M
Estimate at completionSAR 39M
Approved is SAR 3.2M (⁦11.1%⁩) above the estimate
The estimate at completion is SAR 10.2M (⁦35.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2023-11-21⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51007
  • WBS elements⁦5⁩ elements · P-2026-007.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦44⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 640K drawn of SAR 1.6M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 640K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.862.342.342.34⁦−0.48⁩
2Design & permits3.724.684.684.68⁦−0.96⁩
3Civil works11.8014.8314.8314.83⁦−3.03⁩
4MEP works9.316.210.3911.35⁦−2.04⁩
5Handover4.352.840.005.34⁦−0.99⁩
Unallocated contingency0.960.000.000.48⁦+0.48⁩
Total32.0030.9022.2439.02⁦−7.02⁩

Budget split

WBS

SAR 32M

Budget

  • Management & governanceSAR 1.9M⁦6%⁩
  • Design & permitsSAR 3.7M⁦12%⁩
  • Civil worksSAR 11.8M⁦37%⁩
  • MEP worksSAR 9.3M⁦29%⁩
  • HandoverSAR 4.3M⁦14%⁩
  • Unallocated contingencySAR 960K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-02-06⁩+768

SPI(t) ⁦0.58⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SAR 31.7M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 18.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 22.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 32M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−4.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−13.46⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.82
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.58
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 39M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 16.8M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−7.02⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.41
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 39M
  • If the rest goes to planSAR 36M
  • At cost and schedule performanceSAR 51.4M
  • The PM’s bottom-up estimateSAR 39M
  • To stay within SAR 32M, cost performance on the rest must rise to ⁦1.41⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 39M

Variance at completion: ⁦−7.02⁩ SAR M