PRJ-2026-007Critical4ExecutionConstructionStalled
Training & Employment Centre Complex
Remove from watchlistA 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.
Project managerEng. Shahad M. Al-MalkiProject sponsorEng. Turki A. Al-AnaziProgrammeChamber-owned Premises Programme
Early warning: 97% chance of slipping within 30 days
Budget (BAC)
SAR 32M
Actual cost
SAR 22.2M
70% of budget
Progress
57%Awaiting acceptance 10%
Estimate at completion
SAR 39M
SAR +7M
SPI · CPI
0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Forecast finish
2027-06-01
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work31M17 elements
Unallocated contingency960KSAR 1.6M
Budget at completion32MPRJ-2026-007
Weighted progress57%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total57%31.0422.24