Wadi Al-Dawasir Branch Building

Add to watchlist

On hold pending land allocation and the title deed from the owning entity.

Budget (BAC)

SAR 10.5M

Actual cost

SAR 210K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Wadi Al-Dawasir Branch Building

APPROVEDV2Approved ⁦2026-02-27⁩

1Project identity

Required at this stage
Project name
Wadi Al-Dawasir Branch Building
Project code
PRJ-2026-033
Project sponsor
Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa
Project manager
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa
Portfolio & programme
Branches, Service & Training Centres PortfolioChamber-owned Premises Programme
Type & methodology
Construction · Construction
Current phase
3Planning

2Background & rationale

Required at this stage

On hold pending land allocation and the title deed from the owning entity.

3Objectives

Required at this stage
  1. 1The chamber’s services across Riyadh city and its governorates

4Scope

Required at this stage

In scope

  • On hold pending land allocation and the title deed from the owning entity.
  • Saudi Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2Consultant-approved drawings
  3. 3Health & safety requirements

6Deliverables

Required at this stage
1Project management plan⁦2026-04-04⁩
2Main deliverable — stage 1⁦2027-05-10⁩
3Main deliverable — final stage⁦2028-03-03⁩
4Final report⁦2028-06-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-02-27⁩
  2. Contract signed⁦2026-07-15⁩
  3. 50% of works complete⁦2027-05-10⁩
  4. Provisional acceptance⁦2028-04-23⁩
  5. Closure⁦2028-06-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩7.6M
  • Supervision & consulting⁦14.0%⁩1.5M
  • Internal team⁦9.0%⁩945K
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩525K
The owning sector’s approved budgetTotal10.5M

9Timeline

Required at this stage
Start
2026-03-0112 Ramadan 1447 AH
Baseline finish
2028-06-307 Safar 1450 AH
Duration
⁦28⁩ months

10Key risks

Required at this stage
  • HighLate land allocation and title deed from the owning entity in Wadi Al-Dawasir

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the chamber