Riyadh Chamber of Commerce & Industry
Project charter
Wadi Al-Dawasir Branch Building
APPROVEDV2Approved 2026-02-27
1Project identity
Required at this stage- Project name
- Wadi Al-Dawasir Branch Building
- Project code
- PRJ-2026-033
- Project sponsor
- Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa
- Project manager
- Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa
- Project owner
- Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa
- Portfolio & programme
- Branches, Service & Training Centres PortfolioChamber-owned Premises Programme
- Type & methodology
- Construction · Construction
- Current phase
- 3Planning
2Background & rationale
Required at this stageOn hold pending land allocation and the title deed from the owning entity.
3Objectives
Required at this stage- 1The chamber’s services across Riyadh city and its governorates
Serves the strategic objectives:SO-2.3The chamber’s services across Riyadh city and its governorates
4Scope
Required at this stageIn scope
- On hold pending land allocation and the title deed from the owning entity.
- Saudi Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Saudi Building Code compliance
- 2Consultant-approved drawings
- 3Health & safety requirements
6Deliverables
Required at this stage| 1 | Project management plan | 2026-04-04 |
| 2 | Main deliverable — stage 1 | 2027-05-10 |
| 3 | Main deliverable — final stage | 2028-03-03 |
| 4 | Final report | 2028-06-30 |
7Key milestones
Required at this stage- Charter approved2026-02-27
- Contract signed2026-07-15
- 50% of works complete2027-05-10
- Provisional acceptance2028-04-23
- Closure2028-06-30
8Budget
Required at this stage- Main contract72.0%7.6M
- Supervision & consulting14.0%1.5M
- Internal team9.0%945K
- Contingency reserve (5%)5.0%525K
The owning sector’s approved budgetTotal10.5M
9Timeline
Required at this stage10Key risks
Required at this stage- HighLate land allocation and title deed from the owning entity in Wadi Al-Dawasir
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the Government Tenders & Procurement Law
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change CommitteeApproves scope, cost and schedule changesWeekly
- PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly