Wadi Al-Dawasir Branch Building

Add to watchlist

On hold pending land allocation and the title deed from the owning entity.

Budget (BAC)

SAR 10.5M

Actual cost

SAR 210K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦5⁩ mandatory documents due
  • 5 mandatory documents missing
  • No documents

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3PlanningCurrent stage
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4Execution
    • Periodic update cards & status reportsMandatory· Not yet due

      Periodic update card form

    • Deliverable completion certificatesMandatory· Not yet due

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Not yet due

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents0
Linked to tasks0
Tasks with documents0

This project has no documents yet — upload the first one to link it to its stage and tasks.

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 033-D1Project plan & baselinePRJ-2026-033_1.1_v1.pdfApprovedDeliverable
  • 033-D2Monitoring & reportingNo evidence filed yetDraftDeliverable
  • 033-D3Detailed designNo evidence filed yetDraftDeliverable
  • 033-D4Permits & approvalsNo evidence filed yetDraftDeliverable
  • 033-D5Site works & excavationNo evidence filed yetDraftDeliverable
  • 033-D6StructureNo evidence filed yetDraftDeliverable
  • 033-D7FinishesNo evidence filed yetDraftDeliverable
  • 033-D8SupplyNo evidence filed yetDraftDeliverable
  • 033-D9InstallationNo evidence filed yetDraftDeliverable
  • 033-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 033-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 033-D12Final acceptanceNo evidence filed yetDraftDeliverable