SO-2.3 · The chamber’s services across Riyadh city and its governorates

Branches & service points in the industrial cities

Off trackDelivered wholly through projectsA Partner in Growth

The chamber branch and manufacturers’ service centre in the Second Industrial City and the new Premium Members Centre — bringing service closer to manufacturers and key members.

⁦44%⁩

Initiative weighted progress

⁦44.2%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦44.2%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

22.2M

2 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

PRJ-2026-006

Primary⁦60%⁩⁦39%⁩⁦23.4%⁩
New Premium Members Centre & VIP Lounges

PRJ-2026-019

Primary⁦40%⁩⁦52%⁩⁦20.8%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦44.2%⁩ points ÷ shares counted ⁦100%⁩ = ⁦44.2%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦44.2%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

The branch and manufacturers’ service centre in the Second Industrial City, and the new Premium Members Centre and VIP lounges.

Outputs

  • The Second Industrial City branch
  • The new Premium Members Centre

Delivery phases

  • Ground improvement and foundations

    2024-09-01 — 2025-12-31

  • Structure and finishes

    2025-06-01 — 2027-04-30

  • Fit-out and opening

    2027-03-01 — 2027-07-31

Today · ⁦2026-10-28⁩

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

No benefits registered for these projects yet; they are recorded at closure and handover.

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

1Deliverable weight in the project

⁦38.0%⁩

Weight of «Civil works» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦25.2%⁩

Its relative weight in Branches, Service & Training Centres Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦60%⁩

Its contribution to «Branches & service points in the industrial cities»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayHighBeing treated

    Ground improvement delayed the Second Industrial City branch by three months

    Response: A temporary service hall for manufacturers in the city until opening

    Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa

Deviation

Budget: projects total SAR 22.2M against the estimate SAR 21M

Schedule: last project ends ⁦2027-07-04⁩ against the initiative end ⁦2027-07-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Board resolution BRD-1447-092026-03-256 Shawwal 1447 AH

No change requests on this item since the plan was approved.