PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−11

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦95% done against 100% planned⁩.

⁦SPI 0⁩.⁦95⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Improving the OrganisationSO-4.2Streamlined governance and dependable technology

Main initiative

SI-4.1.1Dynamics 365 for resources and members

Contribution to the initiative⁦16%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2025-017
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦95%⁩

Awaiting acceptance ⁦5%⁩

Not handed in ⁦0%⁩

10 deliverables accepted

  • Release 2⁦14%⁩
  • Integrations⁦14%⁩
  • Release 1⁦13%⁩
  • System testing⁦10%⁩
  • User acceptance testing⁦10%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Training & change⁦8%⁩

1 deliverable under inspection or acceptance

  • Go-live & handover⁦5%⁩

Corrective plan requiredThe project is seriously late (46 days late) and has no corrective plan yet.

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦98%⁩ of budget

675K/ 710K
Actual spend
675K
Committed
695K
Approved budget
710K
Estimate at completion
710K

Next milestones

  • Closure⁦2026-11-15⁩was ⁦2026-09-30⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

1 open risk, exposure SAR 24K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0038High UAT defect count in the outgoing-mail moduleProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Deliverables

⁦10⁩ of ⁦11⁩ approved

  • Project plan & baseline017-D1 · V1 · CRT-017-01⁦4%⁩Dana S. Al-Saleh⁦2025-04-14⁩2025-04-1416 Shawwal 1446 AHApproved
  • Monitoring & reporting017-D2 · V1 · CRT-017-02⁦4%⁩Munirah A. Al-Khalidi⁦2025-06-07⁩2025-06-0711 Dhuʻl-Hijjah 1446 AHApproved
  • Business requirements017-D3 · V1 · CRT-017-03⁦9%⁩Munirah A. Al-Khalidi⁦2025-07-30⁩2025-07-305 Safar 1447 AHApproved
  • Solution design017-D4 · V1 · CRT-017-04⁦9%⁩Sarah A. Al-Qarni⁦2025-09-21⁩2025-09-2129 Rabiʻ I 1447 AHApproved
  • Release 1017-D5 · V1 · CRT-017-05⁦13%⁩Sarah A. Al-Qarni⁦2025-11-14⁩2025-11-1423 Jumada I 1447 AHApproved
  • Release 2017-D6 · V1 · CRT-017-06⁦14%⁩Dana S. Al-Saleh⁦2026-01-06⁩2026-01-0617 Rajab 1447 AHApproved
  • Integrations017-D7 · V1 · CRT-017-07⁦14%⁩Munirah A. Al-Khalidi⁦2026-03-01⁩2026-03-0112 Ramadan 1447 AHApproved
  • System testing017-D8 · V1 · CRT-017-08⁦10%⁩Dana S. Al-Saleh⁦2026-04-23⁩2026-04-236 Dhuʻl-Qiʻdah 1447 AHApproved
  • User acceptance testing017-D9 · V1 · CRT-017-09⁦10%⁩Munirah A. Al-Khalidi⁦2026-06-15⁩2026-06-1529 Dhuʻl-Hijjah 1447 AHApproved
  • Training & change017-D10 · V1 · CRT-017-10⁦8%⁩Munirah A. Al-Khalidi⁦2026-08-08⁩2026-08-0825 Safar 1448 AHApproved
  • Go-live & handover017-D11 · V1⁦5%⁩Sarah A. Al-Qarni28 days overdue2026-09-3019 Rabiʻ II 1448 AHSubmitted

Team, contracts & documents

Team

1 member

Dana S. Al-Saleh · Director, Enterprise Systems & Integration
  • Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationProject managerP-025d.alsaleh@chamber.sa⁦25%⁩