Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work688.7K⁦16⁩ elements
Unallocated contingency21.3KSAR 36K
Budget at completion710KPRJ-2026-017
Weighted progress⁦95%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project704⁦2025-01-19⁩⁦2026-12-24⁩⁦95%⁩0.690.68—
1
Phase159⁦2025-01-19⁩⁦2025-06-27⁩⁦100%⁩0.060.06—
1.1
WBS element98⁦2025-01-19⁩⁦2025-04-27⁩⁦100%⁩0.030.030 / 1
1.2
WBS element98⁦2025-03-21⁩⁦2025-06-27⁩⁦100%⁩0.030.031 / 2
2
Phase159⁦2025-05-21⁩⁦2025-10-27⁩⁦100%⁩0.120.12—
2.1
WBS element98⁦2025-05-21⁩⁦2025-08-27⁩⁦100%⁩0.060.061 / 1
2.2
WBS element98⁦2025-07-21⁩⁦2025-10-27⁩⁦100%⁩0.060.061 / 2
3
Phase220⁦2025-09-20⁩⁦2026-04-28⁩⁦100%⁩0.280.28—
3.1
WBS element98⁦2025-09-20⁩⁦2025-12-27⁩⁦100%⁩0.090.091 / 1
3.2
WBS element98⁦2025-11-20⁩⁦2026-02-26⁩⁦100%⁩0.090.091 / 1
3.3
WBS element98⁦2026-01-20⁩⁦2026-04-28⁩⁦100%⁩0.090.091 / 2
4
Phase159⁦2026-03-22⁩⁦2026-08-28⁩⁦100%⁩0.140.14—
4.1
WBS element98⁦2026-03-22⁩⁦2026-06-28⁩⁦100%⁩0.070.071 / 1
4.2
WBS element98⁦2026-05-22⁩⁦2026-08-28⁩⁦100%⁩0.070.071 / 2
5
Phase170⁦2026-07-07⁩⁦2026-12-24⁩⁦67%⁩0.100.07—
5.1
WBS element96⁦2026-07-22⁩⁦2026-10-26⁩⁦100%⁩0.050.051 / 1
5.2
WBS element170⁦2026-07-07⁩⁦2026-12-24⁩⁦33%⁩0.050.021 / 1
Total⁦95%⁩0.690.68
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close