PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-09-30⁩
    Budget
    SAR 710K
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-01-19⁩ · by Sarah A. Al-Qarni

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-12-24⁩
    ⁦+85⁩ days
    Budget
    SAR 710K
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Dana S. Al-Saleh

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-09-30⁩⁦2026-12-24⁩

⁦+85⁩ days

Budget

SAR 710KSAR 710K

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-01
  • Project plan approved⁦+20⁩
  • Designs approved⁦+36⁩
  • Build complete⁦+58⁩
  • Testing & acceptance complete⁦+74⁩
  • Final handover⁦+85⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.00⁩
  • 2Analysis & design⁦+0.00⁩
  • 3Build⁦+0.02⁩
  • 4Testing & acceptance⁦+0.00⁩
  • 5Launch & handover⁦−0.01⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Dana S. Al-Saleh
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-01-19⁩by Sarah A. Al-Qarni