Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+85⁩ days vs approved

Baseline (original = approved)⁦2026-09-30⁩
Current forecast⁦2026-12-24⁩
By earned schedule⁦2027-02-07⁩
Critical activities
2
of ⁦2⁩ open activities
Late activities
1
past their baseline finish
Schedule performance
0.95
earned ÷ planned value
Next milestone
in 57 days
Final handover
Expand allCollapse all
Activity
Correspondence & Document Management SystemPlanned: ⁦2025-01-19⁩ → ⁦2026-09-30⁩Forecast: ⁦2025-01-19⁩ → ⁦2026-12-24⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-01-19⁩ → ⁦2025-06-07⁩Actual: ⁦2025-01-19⁩ → ⁦2025-06-27⁩
Project plan & baselinePlanned: ⁦2025-01-19⁩ → ⁦2025-04-14⁩Actual: ⁦2025-01-19⁩ → ⁦2025-04-27⁩
Monitoring & reportingPlanned: ⁦2025-03-13⁩ → ⁦2025-06-07⁩Actual: ⁦2025-03-21⁩ → ⁦2025-06-27⁩
Project plan approvedPlanned: ⁦2025-06-07⁩ → ⁦2025-06-07⁩Actual: ⁦2025-06-27⁩ → ⁦2025-06-27⁩Project plan approved
Analysis & designPlanned: ⁦2025-05-06⁩ → ⁦2025-09-21⁩Actual: ⁦2025-05-21⁩ → ⁦2025-10-27⁩
Business requirementsPlanned: ⁦2025-05-06⁩ → ⁦2025-07-30⁩Actual: ⁦2025-05-21⁩ → ⁦2025-08-27⁩
Solution designPlanned: ⁦2025-06-28⁩ → ⁦2025-09-21⁩Actual: ⁦2025-07-21⁩ → ⁦2025-10-27⁩
Designs approvedPlanned: ⁦2025-09-21⁩ → ⁦2025-09-21⁩Actual: ⁦2025-10-27⁩ → ⁦2025-10-27⁩Designs approved
BuildPlanned: ⁦2025-08-20⁩ → ⁦2026-03-01⁩Actual: ⁦2025-09-20⁩ → ⁦2026-04-28⁩
Release 1Planned: ⁦2025-08-20⁩ → ⁦2025-11-14⁩Actual: ⁦2025-09-20⁩ → ⁦2025-12-27⁩
Release 2Planned: ⁦2025-10-13⁩ → ⁦2026-01-06⁩Actual: ⁦2025-11-20⁩ → ⁦2026-02-26⁩
IntegrationsPlanned: ⁦2025-12-05⁩ → ⁦2026-03-01⁩Actual: ⁦2026-01-20⁩ → ⁦2026-04-28⁩
Build completePlanned: ⁦2026-03-01⁩ → ⁦2026-03-01⁩Actual: ⁦2026-04-28⁩ → ⁦2026-04-28⁩Build complete
Testing & acceptancePlanned: ⁦2026-01-28⁩ → ⁦2026-06-15⁩Actual: ⁦2026-03-22⁩ → ⁦2026-08-28⁩
System testingPlanned: ⁦2026-01-28⁩ → ⁦2026-04-23⁩Actual: ⁦2026-03-22⁩ → ⁦2026-06-28⁩
User acceptance testingPlanned: ⁦2026-03-22⁩ → ⁦2026-06-15⁩Actual: ⁦2026-05-22⁩ → ⁦2026-08-28⁩
Testing & acceptance completePlanned: ⁦2026-06-15⁩ → ⁦2026-06-15⁩Actual: ⁦2026-08-28⁩ → ⁦2026-08-28⁩Testing & acceptance complete
Launch & handoverPlanned: ⁦2026-05-14⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-07-07⁩ → ⁦2026-12-24⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-05-14⁩ → ⁦2026-08-08⁩Actual: ⁦2026-07-22⁩ → ⁦2026-10-26⁩
Go-live & handoverPlanned: ⁦2026-07-07⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-07-07⁩ → ⁦2026-12-24⁩Float: ⁦0⁩dDrag to change its duration+85
Final handoverPlanned: ⁦2026-09-30⁩ → ⁦2026-09-30⁩Forecast: ⁦2026-12-24⁩ → ⁦2026-12-24⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦2⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦1⁩ activity with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Go-live & handover” needs a pace ⁦4.0⁩× faster than it has kept

It earned ⁦33%⁩ in 113 days; the forecast assumes the rest in 57 days. At the pace so far it finishes on ⁦2027-06-14⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 55 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

20
36
58
74
85
G1G2G3G4G5

The critical chain

In date order, to final acceptance