Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 210K — if approved the value becomes SAR 53.1M
41% of the current value paid
Paid
of a current value of SAR 52.9M
Open claims
1
of 1 claim
Extension days claimed
120 days
If granted, it ends on 2027-10-28
Amounts claimed
SAR 725K
1.4% of the contract value
Extension granted
None
From earlier claims
Extensions of time, cost claims and disputes
CLM-0007Extension of timeIn review
120-day extension with compensation — utility relocation
Utility owners late relocating water and power lines off the HQ site