Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦9⁩ — July 2025

Supervision — chamber investment building

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2025-08-18⁩
Hijri
24 Safar 1447 AH
Reference
PAY-2024-018-09

Interim payment certificate no. (⁦9⁩)

For the work of July 2025

Contract number
RC/2024/018
Supplier-portal reference
2402270238
Contract
Supervision — chamber investment building
Contractor
Bait Al-Khebra Engineering Consultants
Contractor VAT number
310101872060003
Project
The Chamber’s Investment Building — Business Tower on King Fahd Road
Contract period
⁦2024-07-01⁩ — ⁦2027-08-31⁩
Original contract value
470,000
Current contract value
470,000
Linked milestone
Mid-term review · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date117,500
2Less: previous certificates(100,500)
3Value of work in this certificate17,000
4Less: retention (⁦5%⁩)(850)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(850)
8Net before VAT16,150
9Add: value added tax (15%)2,423
10Net amount payable to the contractor18,573

Amount in words: Eighteen thousand five hundred seventy-three Saudi riyals only

Retention held up to this certificate: SAR 5,875 — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff291,40062,70010,60073,300⁦25%⁩
Visiting specialists84,60018,1003,05021,150⁦25%⁩
Laboratory & testing56,40010,8501,85012,700⁦23%⁩
Reporting & technical office37,6008,8501,50010,350⁦28%⁩
Total470,000100,50017,000117,500⁦25%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Nader F. Al-Asiri

Al-Asiri⁦2025-08-18⁩

Supervising engineer

Haifa S. Al-Ruwaili

Al-Ruwaili⁦2025-08-20⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-08-23⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-08-26⁩

Final approver

Munirah A. Al-Khalidi

Al-Khalidi⁦2025-08-29⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-18⁩

    Eng. Nader F. Al-Asiri

  2. Engineer verifies quantities⁦2025-08-20⁩

    Haifa S. Al-Ruwaili · Senior Financial Analyst

    Took 2 days

  3. Project manager certifies⁦2025-08-23⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2025-08-26⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-08-29⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMid-term reviewDone · ⁦2026-01-30⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHaifa S. Al-Ruwaili → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Munirah A. Al-Khalidi

Certificate history

29 August 2025

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2025-08-29 13:00

26 August 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-08-26 13:00

23 August 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-08-23 13:00

20 August 2025

  1. Approval: Haifa S. Al-Ruwaili signed “Engineer verifies quantities”

    2025-08-20 13:00

18 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close