“United Buildings & Operations Co.” is 95 days late and it affects “Converting the Current Headquarters into a Member Services Centre & Committee Rooms” and “New Premium Members Centre & VIP Lounges” and 1 more
Dependencies between projects, programmes and vendors, and knock-on delay.
across 36 items
beyond their float
half the float used
outside the chamber’s control
through delay propagation
When a party’s delay exceeds the float, it carries on to whatever depends on it — these are the chains that need action now
“United Buildings & Operations Co.” is 95 days late and it affects “Converting the Current Headquarters into a Member Services Centre & Committee Rooms” and “New Premium Members Centre & VIP Lounges” and 1 more
“Saudi Electricity Company” is 75 days late and it affects “The Chamber’s New Headquarters Building” and “Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality” and 1 more
“Digital Platforms Solutions Co.” is 43 days late and it affects “My Business Portal 2.0 — the Unified Member Journey” and “Riyadh Chamber Mobile App — New Release” and 1 more
“National Information Center (Nafath)” is 40 days late and it affects “My Business Portal 2.0 — the Unified Member Journey” and “Riyadh Chamber Mobile App — New Release” and 1 more
Tasks, projects, programmes, vendors and external entities — hover an item to see what it depends on and what depends on it, click it for its details
Delay simulator
What if an item slips further? Pick it and a number of days to see how far the effect travels.
Extra delay30 days
Each dependency: who waits on whom, for what, by when, with how much float, and the delay it carries now
Display options
DEP-029 Commissioning passed before handover and the member services centre opens | Building systems commissioning (HVAC & fire)Task | Converting the Current Headquarters into a Member Services Centre & Committee RoomsProject | Finish-to-start | 2026-09-30 | 0 days | 126 days | 126 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa |
DEP-031 More member-service and committee-meeting capacity after rehabilitation | Converting the Current Headquarters into a Member Services Centre & Committee RoomsProject | Building Rehabilitation & Efficiency ProgrammeProgramme | Programme outcome | 2027-03-31 | 30 days | 126 days | 96 days | Late | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa |
DEP-027 Electro-mechanical works complete | United Buildings & Operations Co.Vendor | Building systems commissioning (HVAC & fire)Task | Deliverable | 2026-08-31 | 0 days | 95 days | 95 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa |
DEP-018 HV line diversion in zone 4 | Saudi Electricity CompanyExternal entity | The Chamber’s New Headquarters BuildingProject | Service | 2026-09-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa |
DEP-021 New HQ complete and the chamber’s sectors moved in | The Chamber’s New Headquarters BuildingProject | New Headquarters & Investment Assets ProgrammeProgramme | Programme outcome | 2027-06-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa |
DEP-022 The business tower in service and its space let | The Chamber’s Investment Building — Business Tower on King Fahd RoadProject | New Headquarters & Investment Assets ProgrammeProgramme | Programme outcome | 2027-05-31 | 0 days | 64 days | 64 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa |
DEP-016 Automated financial processes | Chamber ERP on Dynamics 365Project | Enterprise Systems & Dynamics 365 ProgrammeProgramme | Programme outcome | 2026-12-31 | 0 days | 58 days | 58 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa |
DEP-019 Foundations complete before the concrete frame | Foundations of axes 12 to 16Task | The Chamber’s Investment Building — Business Tower on King Fahd RoadProject | Finish-to-start | 2026-12-15 | 0 days | 55 days | 55 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa |
DEP-020 The meeting-room, co-working and security standards approved at the new HQ | The Chamber’s New Headquarters BuildingProject | Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityProject | Finish-to-start | 2027-07-31 | 20 days | 75 days | 55 days | Late | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa |
DEP-003 Wave 1 member service package | Digital Platforms Solutions Co.Vendor | Wave 1 development (24 member services)Task | Deliverable | 2026-09-30 | 0 days | 43 days | 43 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa |
DEP-006 UAT passed before the official launch | User acceptance testingTask | My Business Portal 2.0 — the Unified Member JourneyProject | Finish-to-start | 2027-01-31 | 0 days | 42 days | 42 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa |
DEP-011 Programme target: 85% of member services digital | My Business Portal 2.0 — the Unified Member JourneyProject | Digital Member Journey ProgrammeProgramme | Programme outcome | 2027-03-31 | 0 days | 42 days | 42 days | Late | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the My Business Portal & Programme Manager, Digital Member JourneyP-004r.aldosari@chamber.sa |
DEP-001 A dedicated Nafath test environment | National Information Center (Nafath)External entity | Nafath & Government Service Bus integration completeTask | Service | 2026-10-31 | 0 days | 40 days | 40 days | Late | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.sa |
DEP-005 Developed services ready for testing | Wave 1 development (24 member services)Task | User acceptance testingTask | Finish-to-start | 2026-12-01 | 4 days | 43 days | 39 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@chamber.sa |
DEP-010 My Business service APIs for the mobile app | My Business Portal 2.0 — the Unified Member JourneyProject | Riyadh Chamber Mobile App — New ReleaseProject | Data | 2027-01-15 | 6 days | 42 days | 36 days | Late | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa |
DEP-030 The standard meeting room, proven in the committee-room wing | Converting the Current Headquarters into a Member Services Centre & Committee RoomsProject | New Premium Members Centre & VIP LoungesProject | Service | 2026-12-31 | 92 days | 126 days | 34 days | Late | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa |
DEP-004 UAT cannot start before integration is complete | Nafath & Government Service Bus integration completeTask | User acceptance testingTask | Finish-to-start | 2026-12-01 | 10 days | 40 days | 30 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@chamber.sa |
DEP-013 SADAD link certified for membership and attestation fees | SADAD Payment SystemExternal entity | Chamber ERP on Dynamics 365Project | Service | 2026-10-31 | 0 days | 28 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa |
DEP-015 Cost centres and member invoices from the ERP | Chamber ERP on Dynamics 365Project | Member 360 — Member Relationship Management on Dynamics 365Project | Data | 2027-03-01 | 30 days | 58 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa |
DEP-023 Trenching permits for the network in the districts | Riyadh Region Municipality (trenching permits)External entity | Unified Enterprise Network for HQ & the BranchesProject | Approval | 2026-10-15 | 15 days | 40 days | 25 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa |
DEP-007 Disaster-recovery site for the chamber’s systems | Disaster Recovery Centre for the Chamber’s SystemsProject | Moving the Chamber’s Systems & Website to the CloudProject | Service | 2026-12-31 | 14 days | 38 days | 24 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa |
DEP-002 Updated Government Service Bus interface specification | Government Service BusExternal entity | Nafath & Government Service Bus integration completeTask | Deliverable | 2026-10-20 | 25 days | 23 days | — | At risk | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa |
DEP-008 Production environment in the cloud | Moving the Chamber’s Systems & Website to the CloudProject | My Business Portal 2.0 — the Unified Member JourneyProject | Service | 2027-01-31 | 30 days | 24 days | — | At risk | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa |
DEP-009 Conformance review against the UX standards the chamber adopts | Digital Government Authority (UX standards)External entity | My Business Portal 2.0 — the Unified Member JourneyProject | Approval | 2027-02-15 | 10 days | 0 days | — | On track | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.sa |
DEP-012 The mobile channel in the programme KPIs | Riyadh Chamber Mobile App — New ReleaseProject | Digital Member Journey ProgrammeProgramme | Programme outcome | 2027-01-31 | 40 days | 36 days | — | At risk | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the My Business Portal & Programme Manager, Digital Member JourneyP-004r.aldosari@chamber.sa |
DEP-014 Financial module customisations | Integrated Business Systems Co.Vendor | Chamber ERP on Dynamics 365Project | Deliverable | 2026-11-15 | 30 days | 21 days | — | At risk | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa |
DEP-017 Data governance policies (gate condition) | Business Observatory & Data GovernanceProject | Sectoral Committee Recommendations TrackerProject | Approval | 2027-01-31 | 20 days | 18 days | — | At risk | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa |
DEP-024 The chamber channel studio linked to the secure enterprise network | Unified Enterprise Network for HQ & the BranchesProject | Chamber Channel & Podcast Studio — with a Media SponsorProject | Service | 2027-06-30 | 60 days | 33 days | — | At risk | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@chamber.sa |
DEP-025 Network for the unified contact centre | Unified Enterprise Network for HQ & the BranchesProject | Unified Contact Centre 920004565 & AI AssistantProject | Service | 2027-09-30 | 90 days | 33 days | — | On track | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa |
DEP-026 HQ and branch gate and visitor data into the unified contact centre | Smart Access, Visitor & Event Management at HQ & the BranchesProject | Unified Contact Centre 920004565 & AI AssistantProject | Data | 2027-06-30 | 60 days | 45 days | — | At risk | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa |
DEP-028 Civil Defence safety certificate | General Directorate of Civil DefenceExternal entity | Building systems commissioning (HVAC & fire)Task | Approval | 2026-12-31 | 0 days | 0 days | — | On track | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa |