Contractor claims file — Training & Employment Centre complex
Training & Employment Centre Complex
The parties
This contract is made between the Riyadh Chamber of Commerce & Industry (first party) and the contractor named in the data sheet (second party), under the procurement and contracts regulation approved by the chamber’s board.
- Project
- Training & Employment Centre Complex (PRJ-2026-007)
- Project manager
- Eng. Shahad M. Al-Malki
- Budget
- SAR 32.00M
- Progress
- 57% actual against 82% planned
- Forecast finish
- 2027-06-01
Key terms
- Delay penalty 0.5% a week, capped at 10% of the contract value
- A 5% performance bond valid until final handover
- 10% retention on every certificate
Addendum 1
This addendum amends the payment schedule and adds complementary works within 10% of the contract value.