Closure & handover form — HR Self-Service

InternalApprovedV1

Closure & handover form — HR Self-Service

More

Internal

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

Project Management Office (PMO)

Code
DOC-0309
Version
V1
Date
2025-08-14

Closure & handover form — HR Self-Service

HR Self-Service

⁦1⁩. Executive summary

This report gives the position of HR Self-Service to date: ⁦100% complete against 100% planned⁩, ⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦06⁩, and an estimate at completion of SAR ⁦538K⁩.

Project
HR Self-Service (⁦PRJ-2026-032⁩)
Project manager
Dana S. Al-Saleh
Budget
SAR ⁦570K⁩
Progress
⁦100% actual against 100% planned⁩
Forecast finish
⁦2025-09-21⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Dr. Noura M. Al-Otaibi

Project manager

Dana S. Al-Saleh
Issued from Munjaz — valid only once approved electronically1 / 1