Riyadh ChamberMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Settle the land handover before award, not after

LL-029 · Procurement · High impact · Published

  1. 1ContextThe chamber’s new headquarters in north Riyadh.
  2. 2What happened⁦The site was handed over piecemeal because 14 plots had not yet been released by the bodies that held them⁩.
  3. 3ImpactA ⁦120-day extension claim and SAR⁩ ⁦340K compensation⁩.

Recommendation

Make “land available” a mandatory approval-gate item.

Captured by
Eng. Ahmed Y. Asiri
Date
2025-06-1014 Dhuʻl-Hijjah 1446 AH
Applies to
Infrastructure · Construction

Where it was used (⁦7⁩)