Riyadh ChamberMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Survey the ground before the design freeze

LL-2026-006 · Design · Medium impact · Published

  1. 1ContextThe chamber branch and manufacturers’ service centre in the Second Industrial City.
  2. 2What happenedDigging found soft soil, groundwater and undocumented utility lines; the service-hall building’s foundations were redesigned.
  3. 3Impact⁦An approved variation and a 5⁩-week delay.

Recommendation

Make a geotechnical and utility survey part of feasibility for any new chamber building or extension on an existing site.

Captured by
Eng. Fahad T. Al-Sulami
Date
2026-05-1225 Dhuʻl-Qiʻdah 1447 AH
Applies to
Infrastructure · Construction

Where it was used (⁦2⁩)